Construction Updates
Week of August 18:
- The contractor has been connecting sewer and water services to houses on Mill Street this week.
- The contractor plans to finish the storm sewer on Mill Street next week.
Past Updates
Week of August 4:
- Sanitary sewer mainline installation is about halfway complete on Mill Street.
- The contractor plans to bring another crew onto Quarterline Street to start setting up temporary water services.
- Week of July 28:
- The contractor, Holtmeier Construction, finished the watermain on Mill Street on Monday, July 28
- Sanitary sewer construction was delayed on Tuesday and Wednesday due to weather conditions
- Sanitary sewer construction began Thursday, July 31 on the West end of Mill Street
Week of July 21
- This week, Holtmeier Construction began removing the old watermain pipe and installing a new one. The installation is progressing smoothly, and the crew anticipates completing the watermain work by Monday or Tuesday of next week.