2025 Street & Utility Improvements

Construction Updates

Week of November 10:

  • New sanitary sewer installation began on Wednesday, November 12 at the north end of Kruse Street and will go across Harrison Street.

  • A small section of the watermain on Harrison Street near the railroad will also be replaced.

  • Water service will be shut off for several hours for some properties on Harrison Street north and south of the railroad. Affected properties will be notified of this work.

Past Updates

Week of October 24:

  • Residents that live on Mill Street: please have your cars off the road by Sunday night as Holtmeier will be fine grading the road on Monday. Thank you!
  • Minneopa concrete will start pouring driveways today and into next week on 1st, 2nd, Kruse, and Quarterline Streets.

 

Week of October 13:

    • Railroad boring has been completed

    • Minneopa Concrete will be in town to set up string line for driveways and curb.

Please note: Residents that live on 1st, 2nd, Quarterline, and/or Kruse Streets must have their cars out of their driveways and parked on the road or outside the construction site by 8:00 a.m. on Monday, October 20. They plan to start pouring concrete on Wednesday.

Week of September 29:

  • All underground utility work has been completed, except the north and south alleys of 2nd Street
  • Tree clearing is scheduled to begin soon, to bore under the railroad tracks

Week of September 22:

  • Storm sewer was started on 1st street and will continue into the week of September 29.
  • The contractor finished water services on 2nd Street and Kruse Street.
  • Sewer and water services were completed on Quarterline Street

Week of September 15:

  • Sewer and water utility work is finished on Kruse Street and services will be done by the end of today (September 19).
  • Storm sewer is finished on 2nd Street.
  • All curb, gutter, and driveways are finished on Mill Street.

Week of September 8:

  • The contractor has finished utilities on Mill Street along with water service on 1st, 2nd, Quarterline, and Welcome Streets.
  • Work on Kruse street has begun starting with the watermain.
  • On Monday, September 15 the curb crew will be working on Mill Street.

 

Week of August 18:

  • The contractor has been connecting sewer and water services to houses on Mill Street this week.
  • The contractor plans to finish the storm sewer on Mill Street next week.
 

Week of August 4:

  • Sanitary sewer mainline installation is about halfway complete on Mill Street.
  • The contractor plans to bring another crew onto Quarterline Street to start setting up temporary water services.

Week of July 28:

  • The contractor, Holtmeier Construction, finished the watermain on Mill Street on Monday, July 28
  • Sanitary sewer construction was delayed on Tuesday and Wednesday due to weather conditions
  • Sanitary sewer construction began Thursday, July 31 on the West end of Mill Street

 

Week of July 21

  • This week, Holtmeier Construction began removing the old watermain pipe and installing a new one. The installation is progressing smoothly, and the crew anticipates completing the watermain work by Monday or Tuesday of next week.