Irene Ave, Augusta Ave & Mary Ave Improvements

Project Phasing Map

Proposed Improvements

  • asphalt streets with concrete curb and gutter
  • concrete driveway aprons
  • sanitary sewer system
  • water main, hydrants and water services
  • storm sewer system

Project Updates – June 4, 2024

The paving of the final layer of bituminous pavement is scheduled for Wednesday, June 5 and will continue into Thursday, June 6. Residents should have vehicles removed from the street by 7 AM on June 5 and June 6 so paving operations can be completed.

If the Contractor is not able to complete the paving of the final layer of pavement due to inclement weather or other delays, the paving will occur on the following business day. Paving operations will last two days once operations have begun. Residents will be able to resume regular use of the street the evening following the completion of the paving.

We apologize for any inconvenience this may cause you. If you have any questions or concerns, please contact Nate Thein at (320) 979-9070. Thank you for your patience and understanding throughout the improvement process!

Please refer to the Newly Seeded Lawn Maintenance Guide for turf establishment best practices.

If you have any questions or concerns with the project at this time, please feel free to contact the project engineer, Mitchell Lease, at 320-441-9146 or at Mitchell.Lease@bolton-menk.com.

Sign Up for Project Updates

What to Expect During Construction

Project Contact

Project Contacts

Nate Thein
On-Site Construction Representative
320-979-9070
Nate.Thein@bolton-menk.comĀ 

Mitchell Lease
Project Engineer
320-441-9146
Mitchell.Lease@bolton-menk.com