Project Overview
Project Objectives
- Full reconstruct of 3rd Avenue & 4th Avenue (from 9th Street to 11th Street).
- Improve street surface conditions.
- Replace deteriorating utility infrastructure.
- Enhance the downtown corridor streetscape.
Proposed Improvements – Reconstruction
- Replace all storm sewer, water and sanitary sewer mains and services.
- Construct a new concrete street.
- Construct concrete sidewalks with colored treatments.
- Pedestrian bump-outs at intersections.
- New ornamental street lighting.
Project Area
The project will be performed over two years.
- Phase 1 – 2024 – 3rd Avenue
- Phase 2 – 2025 – 4th Avenue
Contractor
Ideal Construction Group, Inc.
Contact Information
Justin Olson, Sr. Project Engineer
Bolton & Menk, Inc.
507-848-6927
Justin.Olson@bolton-menk.com