3rd & 4th Ave Reconstruction

Top
 

Updates

Project Updates


July 19th, 2024

2024 improvements (Phase 1) will include 3rd Avenue from 9th Street to 11th Street.

Status updates will be posted to the website as the project moves forward.

We appreciate everyone’s patience during the progress of this project. Please contact Bolton & Menk staff (Justin Olson) at 507-848-6927 or the City Engineering office with any questions or concerns.

1st Block – 3rd Avenue (10th Street to 11th Street)

  • Watermain and water services are complete.
  • Sanitary sewer main is complete. The last sanitary service will be completed tomorrow.
  • Storm sewer will be completed today.
  • Frontier is lowering their fiber optic lines and vaults.
  • Sidewalk construction will start next week. Followed by roadway grade preparation.

2nd Block – 3rd Avenue (9th Street to 10th Street)

  • Steam heat system removal and the temporary water services are complete.
  • The Frontier fiber optic line and vault lowering is complete.
  • Water connections and piping are complete within the 9th Street intersection.
  • Sanitary Sewer construction will begin next week. Followed by storm sewer and watermain.
  • Any water shutdown notifications will be issued by the City 24 hours prior to the work.

10th Street Intersection

  • The intersection at 10th Street will remain open until after the Turkey Day celebration.
  • After the Turkey Day weekend, the 10th Street intersection will be closed for removals and
    concrete pavement.

Contractor


Ideal Construction Group, Inc.

Contact Information


Justin Olson, Sr. Project Engineer
Bolton & Menk, Inc.
507-848-6927
Justin.Olson@bolton-menk.com