Construction Update
June 19, 2026
This past week, the Contractor completed pavement restoration within the Andover Clocktower Commons access near Chipotle and the Primrose School. A temporary bituminous roadway was also constructed north of Crosstown Boulevard for use during Stage 1.
The Andover Clocktower Commons access near Chipotle and Primrose School remains closed. The Contractor anticipates reopening this access the week of June 22. Stage 1 is then expected to begin the week of June 22, but will not start until this access is fully reopened to traffic.
Stage 1 work includes constructing the south half of the roundabout along Crosstown Boulevard. Northbound and southbound traffic on Crosstown Boulevard will be maintained. Bluebird Street will be closed south of Crosstown Boulevard.
Click to learn more about construction staging.
All dates are approximate and weather dependent. Thank you for your continued patience during this project.
Past Construction Updates
June 5, 2026
Construction Commencement Notice
The purpose of these notices is to provide a recap of work completed over the past week and outline anticipated work for upcoming weeks. All updates are weather dependent and construction progress dependent.
Over the past several weeks private underground utility work throughout the project area has been ongoing to prepare for the roundabout construction.
The week of June 8, the Contractor will begin roadway construction. Once work starts, the Andover Clocktower Commons access along Crosstown Boulevard, near Chipotle and the Primrose School, will be closed. Signed business access detours will direct drivers to reach the affected businesses. We thank you in advance for your patience and cooperation for the duration of this project.