N 3rd & 4th Avenue Ally Reconstruction

Project Overview

The City of Aurora is planning the reconstruction of the ally between N 3rd Avenue and 4th Avenue, between North 1st Street W and North 4th Street W.  The project will replace the sanitary sewer and service laterals and reconstruct the pavement section.  The project will also include driveway and curb and gutter replacement as necessary and restoration of disturbed lawn areas.

July 2025 – The contractor will begin work on the sanitary sewer, followed by the reconstruction of the alley pavement.

Total Project Cost – $1 Million

Project Timeline

  • Design: Nov 2024 – January  2025
  • Public Hearing – January 21, 2025 (Community Center)
  • Bid Opening: February 2025
  • Assessment Hearing: April 2025
  • Construction: June 2025 – Aug 2025
  • Construction Start: July 7, 2025
  • Roadway Completion: August 29, 2025
  • Sewer Lining Completion: November 30, 2025

Project Updates

Fall 2025 – The contractor will line the sanitary sewer

July 2025 – The contractor will begin work on the sanitary sewer, followed by the reconstruction of the alley pavement.

January 2025 – Project funding has been allocated in the 2025 budget and construction is anticipated for summer of 2025.

December 2024 – Received $200,000 Infrastructure grant from the Iron Range Resource & Rehabilitation Board

June 2024 – The project is not currently funded and the City is actively seeking funding sources to move the project forward.

Click image to view larger.

Click image to view larger.

Sign Up for Project Updates

Contact Us!

For more information or questions regarding this project please contact:

Josh Stier, City Engineer

joshua.stier@bolton-menk.com

Megan McVey, Construction Project Representative

218-830-2769