CONSTRUCTION TIMEFRAME
April 8 – Road Closure State Street from Eagle St to Willow St
Mid-May – Road Closure State Street from Willow St to Chestnut St
End of June – Road Closure State Street from Chestnut St to Walnut St (State St/TH 25 intersection will remain open at all times) / Reopening State Street from Eagle St to Willow St
Mid-Aug – Reopening State Street from Willow St to Chestnut St
Mid-Sept – Mill and Overlay on State Street west of Eagle St
Oct 18 – Substantial Completion / Removal of Detour and Reopening of all of State Street
June 2025 – Final Completion