Diffley Road School Area Safety Improvements
Top
 

Schedule

Construction Schedule

Construction is anticipated to begin in May 2021 and be completed by late fall 2021.

Questions or concerns about construction?

Send them in to the project email or call the project hotline!

Project Email: DiffleyConstruction@bolton-menk.com

Project Hotline: 612-258-2918

Complete Project Timeline

Study: Fall 2019 – Spring 2020
Preliminary design:
Summer – Fall 2020
Final design: Fall 2020 – Spring 2021
Construction: Spring 2021 – Fall 2021