Weekly Update – August 5, 2022

Stage 2A & 3, No. 15

View the available turning movements map near the work area as of August 8.

Week of August 1

  • The contractor worked on installing storm sewer along Ferry Street from Main Street to 2nd Street. Following the completion of the storm sewer, the contractor worked on installing sanitary sewer along Ferry Street up to 3rd Street.
  • The contractor placed black dirt along Main Street from Smith Street to Davis Street.
  • The contractor placed class 5 along Main Street from Davis Street through Cantwell Street in preparation for curb and gutter which is planned for Monday, August 8th.
  • The contractor installed the electric distribution conduit along the west side of Main Street from Davis Street to 2nd Street.
  • The contractor continued pouring sidewalk and driveways along S Main from Smith Street to Davis Street.

Week of August 8

  • On Monday, 8/8, at 7 am, the contractor will be closing Main Street from 2nd Street through the intersection of 3rd Street. Main Street will be closed from Smith Street through 3rd Street at this time. The intersection of Main Street and 3rd Street will remain open to the greatest extent possible. All traffic coming and going into town from the south on CSAH 36 will be detoured via CSAH 22 & CR 115.
  • The contractor will work on installing sanitary sewer along Ferry Street up to 4th Street. Following the sanitary sewer installation, the contractor will work on installing the watermain along Ferry Street from 2nd Street to 3rd Street. After the completion of the watermain, the contractor will work on installing sanitary sewer and water services on Ferry from 2nd Street to 4th Street. The contractor will also work on installing storm sewer on Ferry Street from 2nd Street to 3rd Street.
  • A second utility crew will be onsite working on sanitary sewer and water services along Main Street starting on Tuesday. After completing the services, the contractor will work on installing sanitary sewer, watermain and storm sewer through the intersection of 2nd Street.
  • The contractor will be removing the garage on the east side of Main Street between 2nd Street and Cantwell Street on Monday 8/8.
  • The contractor will start removing pavement and subcutting the road along Main Street from 2nd Street through Maag Street.
  • The contractor will install lighting conduit along Main Street from Davis Street to Cantwell Street. They will also pour light bases along Main Street from Smith Street to Cantwell Street.
  • In addition to pouring curb and gutter on Main Street from Davis Street through Cantwell Street, the contractor will work on sidewalks and driveways through this stretch of roadway.