Construction Updates
2025 Updates
July 25, 2025
Sewer and watermains have been installed from Fairlakes Avenue to Balcom Street. Storm sewer work in this block is scheduled for next week. Please see the construction newsletter for updates on business and residential access under helpful links.
July 3, 2025
Watermain in the Fairlakes intersection has now been completed and the city’s contractor is working on installing sanitary sewer main along the south side of the street up to approximately Rosen’s. Once that is complete, they plan to install watermain to the same point.
After the pipe has been installed a temporary gravel surface will be placed so traffic can be routed down the south side of street rather than the north to get pavement removed on the north side.
The city’s contractor has tentatively planned to start removals of the north pavement at the Fairlakes intersection working to the west. They plan to remove pavement as pipes are installed, and temporary gravel is installed on the south side. We would anticipate this taking a week or two. The contractor will likely be using flaggers or temporary signal lights alternating with one-way traffic during portions of this work.
Removal of pavement is tentatively scheduled to begin on Monday July 7th depending on the pipe installation progress and weather.
We appreciate your patience as we work on this project. All work is weather dependent and subject to change.
June 4, 2025
Construction start date is set for Monday, June 9th. The neighborhood meeting is being held tonight, June 4th.