Construction activities can be greatly influenced by differing site conditions, weather or other unforeseen issues that may cause deviations from the proposed schedule. The following is the contractor’s tentative schedule.
Week of April 8th
Contractor will layout temporary water system pipe through backyards
Week of April 15th
Reclaiming and removing pavement (streets and driveways)
Week of April 22nd
Tree removal – entire project
Connect residents to temporary water
Week of April 29th
Sewer and water construction – Westdel Road
Sewer construction at Denmark & Hickory
Week of May 6th
Sewer and water construction – Hickory Street
Curb & Gutter – Westdel Road
Week of May 13th
Sewer and water construction – Hickory Street
Driveway replacement – Westdel Road
Week of May 20th
Sewer and water construction –Hickory Street
Pavement & restoration – Westdel Road
Late May through mid July
Reclaiming & removing pavement – Westview Drive, Westwood, Westlyn, Westgail Court
Sewer and water reconstruction – Westview Drive, Westwood, Westlyn, Westgail Court
Mid July through Mid August
Road reconstruction & restoration – Westview Drive, Westwood, Westlyn, Westgail Court