Construction Update
June 28, 2019
Construction Completed This Week
- RL Larson continued grading for reconstruction of Hickory Street and the cul-de-sacs
- RL Larson completed installation of the storm sewer along the school property and First Street
- RL Larson installed all the sanitary sewer and watermain on Westdel Road
- Northern Dewatering installed dewatering equipment on Westview Drive
Scheduled Construction Next Week
- RL Larson will install all sanitary sewer and water services on Westdel Road
- RL Larson will install the storm sewer on Westdel Road
- RL Larson will continue street reconstruction on Hickory Street and cul-de-sacs
June 7, 2019
Construction Completed This Week
- RL Larson has installed all of the sanitary sewer and watermain services on Hickory Street
- RL Larson has installed all of the sanitary sewer, watermain and services on Westwood Court
- RL Larson has started installing the storm sewer on Hickory Street
- NPL continues to install new gas main and connections to homes
News & Notes
- Reminder: Call Bob at (320) 241-5561 with any sewer or water service issues during construction
- Reminder: There is No Parking on County Roads; Residents should avoid parking on school property, as it can block bus traffic; parking is available in the St. Michael’s parking lot during construction hours.
- Construction on Westdel Road will not take place according to the original schedule; sewer and water construction on Westdel Road is tentatively scheduled for mid-July
Contacts
Should property owners have any questions about this information or the project in general, please contact Shawn Snyder at (651) 755-1497 or Eric Hauser at (507) 276-6695.
Thank you for your patience, cooperation, and understanding throughout the process of improving your streets and utilities!