Construction Updates
A phased construction schedule has been proposed by Northwest Asphalt as shown in the Phasing Map at the bottom of this page. The following is an overview of the upcoming project schedule:
Week of October 28th
- Topsoil installed on Cambridge St (Stages 4A & 4B).
- The final layer of asphalt will be paved on Cambridge St (Stages 4A & 4B) on Saturday, November 2nd.
Week of November 4th
- Turf restoration will wrap up on Hiawatha Ave (Stage 3) and Cambridge St (Stages 4A & 4B).
Mid-November and/or Early Spring (Weather Permitting)
- Clean-up work throughout the project area
- Pavement striping throughout the project area