Construction Update

Week of September 26th

  • Contractor patched the curb on Mainstreet with new asphalt and reopened all parking stalls.
  • The final layer of asphalt was paved on 6th Avenue.

Week of October 3rd

  • Crosswalks will be restriped on 7th Ave and 6th Ave.