Week of May 9th
- Contractor performed street patching at new concrete areas.
- Contractor conducted milling operations which removed 1.5″ to 2″ of existing asphalt pavement.
Week of May 16th
- Contractor will remove and patch any defective roadway pavement.
- Contractor will conduct final paving operations either Thursday or Friday (5/19 and 5/20).
Week of May 23rd
- Contractor will permanently stripe the roadway.
6th Ave & 7th Ave
Phasing Information
Click here to view the phasing map.
Construction Update
Week of May 9th
- Gas main and service replacement by CenterPoint Energy and Michels continued on 7th Avenue S.
Week of May 16th
- Gas service replacements on 7th Avenue.
- Steel gas main replacements to start on Thursday on the north end of 7th Avenue.
- Roadway closure at 7th Avenue and Mainstreet for the steel gas main replacement/connections.
- CenterPoint Energy Contact:
- Hannah Gullickson | 612-321-5546 | Hannah.Gullickson@CenterPointEnergy.com
Week of May 23rd
- Steel gas main replacement will continue and may be completed at the end of the week.
- Restoration of sidewalks and roadways impacted by gas main work.