2024 Central Avenues Improvements

Top
 

Construction Updates

Construction Updates

May 24, 2024

Phase 1A Concrete Next Week!

Week of May 20

  • Roadway grading continued on Phase 1A, wet weather prevented the contractor from finishing and delayed concrete installation.
  • Phase 1B houses were hooked up to the temporary water system.
  • Utility work began on Phase 1B, starting at the north end of 7th Avenue N.
  • Intersection of Minnetonka Mills Rd & 7th Avenue N. has been temporarily closed while construction activities occur within the intersection. A detour route has been put in place.

Week of May 27

  • No work will be occurring on Monday, May 27 for the Memorial Day holiday.
  • Roadway grading will wrap up on Phase 1A.
  • Concrete curbing and driveways will be poured on Phase 1A.
  • Utility work will continue on Phase 1B (north end of 7th Avenue N.)

Attention: On street parking will no longer be available on Phase 1A and Phase 1B during the working day. Working hours are 7:00 am – 7:00 pm Monday through Friday. Also, please refrain from driving through the construction zone as much as possible, road closed to thru traffic signs have been installed to deter unnecessary traffic driving into the construction zone.

Project Phasing Map:

Click map to view larger