Highway 169 and County Road 4 Improvements
Top
 

Home

Traffic impacts

The bridge deck was poured this week.255th Avenue / Highway 169 closure begins July 22

Beginning Wednesday, July 22, weather permitting, 255th Avenue will close between Faith Community Lutheran Church and Morrison Avenue (2nd Street south of Main Street). Residents will still be able to access the church from Highway 169. Use Morrison Avenue to access the compost site. Please do not enter private driveways.

Main Street / County Road 4 closure begins July 27

On Monday, July 27, the Main Street / County Road 4 intersection will close as crews begin work in the area. The 2nd Street intersection will reopen at this time. The Main Street closure is anticipated to remain in place for approximately three weeks.

2nd Street / County Road 4 remains closed

Curb and ramp construction is underway. The intersection expected to reopen on Monday, July 27, weather permitting.

Morrison Avenue (2nd Street south of Main Street) remains closed

Crews are completing storm sewer work and utility improvements. Morrison Avenue is expected to reopen on Wednesday, July 22, weather permitting.

269th Avenue remains closed

Drainage installation and roadway preparation activities continue.

Access compost site via 255th Ave

When heading West on 255th Ave, please keep left and follow signage to the compost site. Do not enter private driveways.

Roadwork

The bridge deck was successfully poured this week, marking a major project milestone. Crews will begin curing operations and continue work on approach panels and bridge elements over the coming weeks.

Embankment construction and retaining wall work continue north and south of the bridge. Most retaining wall construction is expected to be substantially complete by the end of next week.

Curb and gutter installation is planned at several locations, including the east roundabout and northbound entrance ramp area.

Utility work

Utility crews are making progress in multiple areas, including Morrison Avenue, 269th Avenue, north of the bridge, and along County Road 4.

Safety reminder

Drivers may experience heavier congestion during peak travel times due to construction activity and seasonal traffic.

Motorists, cyclists, and pedestrians are encouraged to slow down, follow posted signage, and use designated crossings.

Crews are actively monitoring traffic operations and making adjustments to improve safety and visibility.

Thank you for your patience as we continue to work on this important project.

Access map

Highway 169 / County Road 4 access map

Detour information

Highway 169 reduced to one lane

Highway 169 between 255th Avenue and 269th Avenue has been reduced to one lane and traffic has been shifted to the southbound lanes through August. With this traffic shift, the County Road 4 turn lanes off of Highway 169 will also close through August.

Access east of Highway 169

Eastside access to/from Highway 169 will be maintained via Fremont Drive and a temporary traffic signal at the Highway 169 / Pine Street intersection. The Oak Street access to Highway 169 is permanently closed.

Access west of Highway 169

Westside access to/from Highway 169 will be maintained via Main Street with a temporary traffic signal at the Highway 169 / Main Street intersection. Access to 5th Avenue North (near the Caribou Coffee), Gateway Drive and the newly constructed 255th intersection will remain open as well.

County Road 4 intersection closures

  • The intersections of County Road 4 and Main Street, 2nd Street, and 3rd Street will be intermittently closed throughout the summer. Closures will not overlap. We will share information about these closures once they get closer.
  • The County Road 4 / 3rd Street intersection is currently closed for 3 to 4 weeks for underground utility work.
  • Drivers can utilize nearby roads to access businesses in the area. Access signs will be installed to help drivers navigate the area.

Morrison Avenue (2nd Street south of Main St) closed through spring

253rd Avenue access

  • The frontage road access onto Highway 169 north of 253rd Avenue is permanently closed. Traffic will exit and enter via 253rd Avenue.

255th Avenue access

257th Avenue access

  • 257th Avenue will now access Highway 169 via 121st Street, directly across from 255th Avenue.

269th Avenue will remain closed through the spring

Project email/text updates

Sign me up!

Contact Us


Project Email & Hotline

[email protected]

(763) 463-7818

 

Business Liaison

[email protected]

(763) 248-1697