City of Lake Elmo

2026 Street And Utility Improvements

Upcoming Meetings

 

Past Meetings

Lake Elmo 2026 Street Improvements Neighborhood Construction Open House

Thursday, April 30

Lake Elmo City Hall (3880 Laverne Ave N, Lake Elmo, MN 55042)

Click to see the presentation

Project Updates

Phase 1 non-wear paving has been delayed to Friday, May 29. Innsdale Ave N south of 27th Street N will not be paved on May 29. A revised schedule will be provided once more info is available.

Phase 1 (Inwood Ave N, Innsdale Ave N, Imperial Ave N Cul-De-Sacs)

  • The first layer of asphalt pavement is scheduled for Friday, May 29, weather depending. Click to see the flyer with paving information.
  • Phase 1 mailboxes will be reset on Friday, May 29. If you have removed your mailbox from your yard, please return it to the project area as soon as possible.
  • Asphalt driveway aprons are scheduled to be replaced beginning Monday, June 1. Work at the foot of your driveway may temporarily block access, but no full closures are planned.
  • Week of June 1 – Phase 1 sod restoration is estimated to begin Tuesday, June 2, weather depending.

Phase 2 (27th St N, 26th St N, Imperial Ave South of 26th St N)

  • A construction flyer has been distributed to Phase 2 properties. Click to view the construction flyer.
  • Week of May 28 – Phase 2 mailboxes will be removed on Friday, May 29 and the temporary mailbox bank will be set up on Innsdale Ave N south of 27th Street. A temp mailbox location map is included in the construction flyer.
  • Week of June 1 – Reclaiming of the remainder of Phase 2 streets is scheduled for Thursday, June 4, weather depending.