Project Updates
April 26, 2024:
Work Completed this Week
- Contractor completed this stage’s dewatering system.
- The existing gravel was removed from the road.
- Temporary water system will be set up. The contractor will reach out next week to properties to be connected.
- 292nd St (CSAH 88) was hard closed to traffic.
- Residents within the construction area will have access to their driveways outside of work hours.
Upcoming Construction Work
- Sanitary Sewer Pipe Installation will begin.
- Trenchless installation of sanitary sewer across the railroad will begin.
- A short-term water shut off will occur on Monday April 9th from 9:00 AM – 2:00 PM for work on the watermain for properties around and east of the railroad tracks. Properties affected by the shut down were notified today with a flier on the front door.
News & Notes
- The staging plan has changed from last year. The updated staging plan has been included in the newsletter and can be found on the home page.
- Downtown Businesses are still open during construction. View the business access map HERE.
Thank you in advance for your cooperation!