Project Update – September 13, 2024
Work Completed This Week
- Sanitary sewer main construction on Stage D (292nd St East of the railroad to Duncan) began and was completed.
- Storm Sewer Construction in Stage C (Danel to Cooper) continued
- Street construction on Stage C continued
- Curb and gutter was poured in the intersection of Dickman and 292nd St
Construction Work Next Week
- Storm Sewer Construction in Stage C (Danel to Cooper) will continue
- Street construction on Stage C will continue
- Sewer & Water Service Construction on Stage D (292nd St East of the railroad to Duncan) is expected to begin on Monday
- Retaining wall construction is expected to begin
- Stage E (Duncan to Hwy 56), Stage N (Douglas), and Stage L (Distad) will be grounded into gravel in preparation for sewer construction
- Stage N sanitary sewer construction could begin late next week, weather permitting. If the contractor is unable to start this work next week, it will wait until after Stage E
Upcoming Construction Work
- Sanitary Sewer Construction on Stage E is expected to begin in one week
- Sidewalks on Stage A will be completed after retaining wall construction (1-2 Weeks)
- Bituminous paving on Stage B (Dickman to Danel), Stage I (Dixie), intersection of Dawson/292nd st, and the intersection Dickman/292nd St are expected to be paved in 1-2 weeks
News & Notes
- The primary access to the School for the next few weeks will be via Dickman to 290th St and south on Davisson Ave. A link to an access map to the school can be found HERE