City of Randolph Sanitary Sewer Project
Top
 

Project Updates

Project Updates

July 26, 2024:

Work Completed This Week

  • Storm Sewer installation on Stage A (Dickman to Dawson) was completed
  • Storm Sewer main installation on Stage B (Dawson to Danel) was completed
  • Street base materials on Stage A were installed in preparation for curb & gutter
  • Street construction on Stage B began
  • Pits for the trenchless railroad pipe crossing on Dixie Ave were dug in preparation for the crossing construction next week

Construction Work Next Week

  • Concrete curb & gutter is expected to be installed on Stage A on Monday
    • Affected properties have been notified
    • Pedestrian access to downtown businesses will be maintained during this time
  • Concrete driveways in Stage A are expected to be poured
  • Sidewalks in Stage A will be prepped
  • Street work on Stage B will continue
  • The trenchless railroad pipe crossing on Dixie Ave will begin
  • The contractor continues to pump down ground water on Stage D & G and is looking to resume sanitary sewer construction late next week
    • Sewer Construction on Stage G (Dawson between 292nd & 290th) will start 1-2 weeks after Stage D begins

Upcoming Construction Work

  • Street Paving on Stage A 291st is expected to occur 1-2 weeks
  • Sidewalks and restoration on Stage A will occur in the next 1-2 weeks
  • Concrete curb & gutter on Stage B is expected soon

 News & Notes

  • Reminder: Dakota County is offering grants for sanitary sewer connection.  To date the County has only received 3 applications. Applications are due by the end of 2024.
    • Information on the grant can be found HERE
    • The grant application can be found HERE