Construction Updates
Jul 1, 2025
- Private utility contractors are nearing completion of their relocation work.
- The street and utility contractor, Snow Contracting, plans to begin work in mid-July. They plan to grind the existing pavement on July 14th (weather dependent). Removal and utility work in the Section Avenue and Tracy Road intersection will follow.
- A newsletter will be sent out with a phasing map and additional information.
May 29, 2025
- Private utility contractors to begin relocation work ahead of the street and utility project as early as next week (6/2/2025). Utility companies will contact you directly if they expect any service interruptions. There may be some temporary driveway impacts during the day.
- Street and utility contractor schedule will be provided within the next few weeks.
May 1, 2025
- The street and utility contractor plans to start construction work towards the end of June.
- Over the next several weeks, private utility companies may be completing some of their relocation work. Utility companies will contact you directly if they expect any service interruptions. During this time, there should be no impacts to driveway access.