Newsletters
Weekly Update – May 30, 2025
Project Progress Update
Storm sewer is all that remains for underground along Cleveland between 1st Street and 2nd Street NW. The temporary pavement that was placed last year through the 2nd Street NW intersection, west to the end of the new curb, will be removed early next week to complete the storm sewer. Once storm sewer is complete, the crew will work on sanitary sewer in the east block to 169. Watermain and storm sewer will follow soon behind. Temporary water will be installed and tested next week in that block. A watermain shutdown that will only affect blocks of Main Street north of 1st Avenue SW is anticipated the week of June 9. Notice is planned to be given 48 hours in advance of that shutdown.
Grading crew is subcutting 2nd Street SW today. Plan to install subdrain tile early next week. They plan to move to 1st Street next and then finish up behind the underground crew on Cleveland Ave.
Click below to sign up for project updates!
Contact Us!
Emma Sullivan
On-site Construction Representative – Bolton & Menk, Inc.
507-810-9158
Matthew Cole
City Engineer – Bolton & Menk, Inc.
507-848-5208