Newsletters
Weekly Update
August 21, 2025
Paving 2025 Phase Monday 8-25
Ulland is currently fine grading the aggregate base in preparation for paving this coming Monday, August 25. Paving is expected to only take Monday to complete. Please plan to have all vehicles off the roadway by 6:30 a.m. The road will be reopened later in the day for access.
The detour on 1st Avenue NW will be back in place for paving across the road at 1st Street. Please follow the detour route signage. This detour is anticipated to only be in effect on Monday.
Rain over the weekend pushed the black dirt work to next week. Final topsoil placement, grading and seeding are expected the week of August 25 for the entire project area.
Click below to sign up for project updates!
Contact Us!
Emma Sullivan
On-site Construction Representative – Bolton & Menk, Inc.
507-810-9158
Matthew Cole
City Engineer – Bolton & Menk, Inc.
507-848-5208