Cleveland Ave W Street & Utility Improvements Project
Top
 

Updates

Weekly Updates

May 23rd, 2024

Underground Work Update

Due to the heavy rains this week, the watermain boring company (Lester’s Water Works) was not able to install the trenchless watermain.  They plan on arriving next Wednesday, May 29th, to begin installation on 8th Street.

Both bacteria tests taken on the new watermain passed this week, so Ulland was able to start sanitary sewer service and water service installation on Cleveland Avenue.  They will continue working on services next week followed by storm sewer installation.  There will be no crews working on Memorial Day.

As always, please check the conditions of the road before attempting to drive your vehicles down it.  The weather has not cooperated for anyone, and we thank you for your continued patience while we work to make progress on the project.

Enjoy the Memorial Day Weekend!

May 17th, 2024

Underground Work Update

Ulland has completed watermain installation on Cleveland Avenue from 8th Street to 6th Street, and on 6th Street.  The bacteria tests on the watermain will be taken at the beginning of next week, and once they pass, households will be switched from temporary water to the new watermain after service installation.  Sanitary service and water service installation will begin next week where watermain and sanitary sewer main has been installed.  The new sanitary sewer services and water services will be installed from the new mains to the ROW line for each home.  The City will televise the sewer services at that time, and if you have private work that needs to be complete, you will get a letter from Bolton & Menk with more information.  Ulland also plans to begin storm sewer installation at the end of next week on Cleveland Avenue and 6th Street.

Ulland’s subcontractor (Lester’s Water Works) will be working on 8th Street next Tuesday and Wednesday to bore the new watermain down 8th Street.  This requires minor disturbance to the road, but there will be construction traffic on 8th Street these two days.  Please drive with care while using 8th Street next Tuesday and Wednesday.

Michels Utility Services has finished boring in gas services and will move out of town today.  They will have a restoration crew in town within the coming weeks to fix any disturbances to your property that they caused during their work that will not be restored with the remaining phases of Ulland’s work.

Click below to sign up for project updates!


To sign up for project updates, please enter your contact information below.

Contact Us!


Dustin Meyer

On-site Construction Representative – Bolton & Menk, Inc.

Dustin.Meyer@bolton-menk.com

507-432-8103

Matthew Cole

City Engineer – Bolton & Menk, Inc.

Matthew.cole@bolton-menk.com

507-848-5208