November 4, 2024 – November 8, 2024
This will be the last newsletter on the project. The remaining work on the project consists of the following:
- Completion of all driveway work.
- Backfilling and grading work behind the curb.
- Seeding and mulching behind the curb.
- Sanitary sewer manhole lining.
October 28, 2024 – November 1, 2024
- Paving of the bituminous driveways will begin Monday. Because of the number of driveways, this work may carry into Tuesday.
- Paving of bituminous wear course will occur on Wednesday, weather permitting. There is a forecast for rain next week, which could impact the schedule.
- Grading work behind the curb will be ongoing until completed. Seeding and mulching will occur after grading is completed, but grass growth is not expected until spring.
October 21, 2024 – October 25, 2024
For the week of October 21, expected work includes the following:
- Paving of the bituminous base course is expected to begin Monday afternoon and be completed on Tuesday.
- Raising of manhole and valve castings will follow the paving work.
- Paving of bituminous driveways is expected before the end of the week.
- After the base course paving is completed, the Contractor will complete the backfilling and grading behind the new curb and prepare these areas for seeding and hydro-mulching.
October 14, 2024 – October 18, 2024
For the week of October 14, expected work includes the following:
-
- Grading of the roadway between the new curbs in preparation for bituminous paving.
- As of today, we don’t have a confirmed date for when paving will occur. At this point, we believe it will be sometime the week of October 21st.
- After the base course paving is completed, the Contractor will complete the backfilling and grading behind the new curb and prepare these areas for seeding and hydro-mulching.
October 7, 2024 – October 11, 2024
For the week of October 7, expected work includes the following:
-
- Completion of excavation and building of aggregate road base on Terrace Drive, Oak Street, Pine Street and Isle Road.
- Curb and Gutter construction on these remaining street segments is currently scheduled for Wednesday, October 9.
- After the curb is poured, vehicles will not be able to drive over it until the concrete is cured (along with the concrete driveways for those situations), which takes approximately 5 to 7 days.
- Bituminous paving is tentatively scheduled to begin sometime the week of October 14th.
September 30, 2024 – October 4, 2024
For the week of September 30, expected work includes the following:
-
- Water service construction on Isle Road.
- Storm Sewer construction on Isle Road and Terrace Drive.
- Excavation and building of aggregate road base on Terrace Drive and Oak Street.
- Shayne Imre is filling in for Al this week. If you have any on-site questions, you can contact him at 952-254-1276.
Click below to sign up for project updates!
Contact Us!
Kevin Bittner
Principal Engineer
Bolton & Menk
612-270-6926
Al Spilles
Construction Project Rep.
Bolton & Menk
alan.spilles@bolton-menk.com
612-756-3143