Weekly Updates
July 29, 2024 – August 2, 2024
- Watermain and storm sewer installation will continue working west on Fremont Lane.
- Temporary water is being set up on Pine Street, Terrace Drive and Oak Street, so that the contractor is prepared to move into the next phases of the project.
- Sanitary sewer forcemain construction on Pine Street and Terrace Drive may start late in the week, but more likely will start the following week.
July 22, 2024 – July 26, 2024
- The focus this week will be on watermain installation, picking up from the first stage of installation at 12167 Fremont Lane and working west from there.
- Underground utility installation is complete on the first phase of the project on the east end of Fremont Lane and work to reestablish the roadway will get underway.
- We are communicating with the garbage haulers to make sure everyone’s trash is getting picked up.
July 15, 2024 – July 19,2024
- Installation of storm sewer on the east end of Fremont Lane.
- Installation of watermain services and curb stops where the new watermain has been installed.
- Reclaiming of the existing bituminous pavement on the rest of Fremont Lane as well as on Terrace Drive, Oak Street, Pine Street and Hillside Drive.
- Lining of the existing sanitary sewer on Terrace Drive and a portion of Fremont Lane.
Click below to sign up for project updates!
Contact Us!
Kevin Bittner
Principal Engineer
Bolton & Menk
612-270-6926
Al Spilles
Construction Project Rep.
Bolton & Menk
alan.spilles@bolton-menk.com
612-756-3143