Project Update – October 11, 2021

Ongoing Work (subject to change, weather dependent)

2021 Pavement Management Project
All Phases
  1. The project is mostly complete, with some minor work remaining. Punch list and clean up work will be on-going as well. Any other work or updates will be announced as they occur.

2021 Mill & Overlay Project
  1. The project has been mostly completed. The project crew was out last week doing some restoration seeding and will be returning soon to finish remaining spots.

 

Project Notice – September 27, 2021

Additional Arbor Meadows Park Information

Construction of the Arbor Meadows Park shelter exterior has concluded. The remaining shelter structure is being completed as a part of a different contract with a different contractor. We do not have updates for the schedule at this time, but will send out updates on this work as they become available.

Thank you for your patience!

Project Summary

The 2021 Pavement Management Project includes the rehabilitation of the Pine Meadows 2nd, 4th, and 5th Additions; Sandy Hills 7th and 8th Additions; and East Meadow Cliff neighborhoods, along with Jamaica Avenue from 80th Street to Indian Boulevard, as shown in the Location Map below. The rehabilitation of these areas include full depth pavement removal and replacement, and spot sidewalk and concrete curb and gutter replacement. Minor spot utility repairs will be performed as needed on water main, sanitary sewer, and storm sewer. Also included in this project is:

  • Park improvements to Arbor Meadows Park, including full depth pavement replacement and spot curb to the parking lot.
  • Parking lot improvements to River Oaks Golf Course including full depth pavement replacement, sidewalk removal and replacement, and spot concrete curb and gutter replacement.

Documents

2021 Pavement Management Project Brochure:

Click here to view.

2021 Pavement Management Project Feasibility Study:

Click here to view.

Pine Meadows and Sandy Hills Special Benefit Appraisal:

Click here to view.

East Meadow Cliff Special Benefit Appraisal:

Click here to view.

Project Schedule

  • August 19, 2020 – Council Orders Feasibility Report
  • December 2, 2020 – Council Receives and Approves Feasibility Report/Council Sets a Public Improvement Hearing Date
  • December 10, 2020 – Hold Neighborhood Meeting
  • January 6, 2021 – Council Holds Public Improvement Hearing/Council Orders the Preparation of the Plans and Specifications
  • March 3, 2021 – Council Approves the Plans and Specifications
  • March 25, 2021 – Project Bid Date
  • April 7, 2021  – Contract Award
  • Spring 2021 – Begin Construction
  • September 2021 – Complete Construction
  • September 2021 – Council Sets Assessment Hearing Date
  • October 2021 – Council Holds Assessment Hearing

Location Map

Contact Us!

Have any questions about construction? Call the project hotline to leave a voicemail and a member of the project team will get back to you as soon as possible. We are also reachable by email. See contact info below.

Hotline Phone Number: 763-242-0780

Hotline Email Address: cg2021@bolton-menk.com