2024 Street & Utility Improvement

Top
 

Updates

Initial Public Hearing

10-16-2023 Hearing Presentation

Weekly Updates

July 5, 2024

Due to the weather experienced earlier in the week, and the Holiday, pavement removals of Phase 2 have been pushed back to next week. It is anticipated that pavement removals along Rice Street from 5th Street to 2nd Street will begin on Monday, July 8th. Underground construction in Phase 2 will begin shortly after. A separate grading crew will also be in town restoring Rice Street from 7th Street to 5th Street.

We hope you all had a great 4th of July. Enjoy the weekend!

Click below to sign up for project updates!


Sign up for project updates

To sign up for project updates, please enter your contact information below.