Highway 169 and County Road 4 Improvements
Top
 

Home

Upcoming traffic impacts

Girder placement on the bridge was finished this week.With the Fourth of July holiday approaching, traffic volumes are expected to increase throughout the area. Motorists, cyclists, and pedestrians are encouraged to slow down, stay alert, follow posted signage, and use designated crossings.

255th Avenue / Highway 169 closure begins July 13

Beginning Monday, July 13, weather permitting, 255th Avenue will close between Faith Community Lutheran Church and Morrison Avenue (2nd Street south of Main Street). Residents will still be able to access the church from Highway 169. Use Morrison Avenue to access the compost site. Please do not enter private driveways.

2nd Street / County Road 4 remains closed

The 2nd Street intersection is currently closed while crews work on excavation and utilities.

3rd Street / County Road 4 is open

Crews are finishing paving at this intersection.

Morrison Avenue (2nd Street south of Main Street) remains closed

Morrison Avenue will reopen in mid-July from Main Street to the compost access point. Crews continue water main and storm sewer installation.

269th Avenue remains closed

This week crews are wrapping up paving and concrete driveway placement.

MnDOT cable median project

Motorists may encounter periodic lane closures on Highway 169 south of Zimmerman as the Minnesota Department of Transportation installs high-tension cable median barrier. Read more on MnDOT’s website.

Access compost site via 255th Ave

When heading West on 255th Ave, please keep left and follow signage to the compost site. Do not enter private driveways.

Roadwork

Bridge construction has reached a major milestone. Crews completed girder installation and began placing the bridge deck this week.

Embankment construction continues north and south of the bridge.

Crews continue grading, drainage installation, and roadway preparation work at the Highway 169 entrance and exit ramps. Additional paving work is underway and will continue into early July.

Retaining wall construction remains underway, with crews continuing panel installation over the next several weeks.

Utility work

Utility crews continue to work in multiple areas, including Morrison Avenue and along County Road 4. Upcoming work includes continued water main installation, storm sewer construction, and utility relocations.

Safety reminder

Drivers may experience heavier congestion during peak travel times due to construction activity and seasonal traffic.

Motorists, cyclists, and pedestrians are encouraged to slow down, follow posted signage, and use designated crossings.

Crews are actively monitoring traffic operations and making adjustments to improve safety and visibility.

Thank you for your patience as we continue to work on this important project.

Access map

Highway 169 / County Road 4 access map

Current traffic impacts

Highway 169 reduced to one lane

Highway 169 between 255th Avenue and 269th Avenue has been reduced to one lane and traffic has been shifted to the southbound lanes through August. With this traffic shift, the County Road 4 turn lanes off of Highway 169 will also close through August.

Access east of Highway 169

Eastside access to/from Highway 169 will be maintained via Fremont Drive and a temporary traffic signal at the Highway 169 / Pine Street intersection. The Oak Street access to Highway 169 is permanently closed.

Access west of Highway 169

Westside access to/from Highway 169 will be maintained via Main Street with a temporary traffic signal at the Highway 169 / Main Street intersection. Access to 5th Avenue North (near the Caribou Coffee), Gateway Drive and the newly constructed 255th intersection will remain open as well.

County Road 4 intersection closures

  • The intersections of County Road 4 and Main Street, 2nd Street, and 3rd Street will be intermittently closed throughout the summer. Closures will not overlap. We will share information about these closures once they get closer.
  • The County Road 4 / 3rd Street intersection is currently closed for 3 to 4 weeks for underground utility work.
  • Drivers can utilize nearby roads to access businesses in the area. Access signs will be installed to help drivers navigate the area.

Morrison Avenue (2nd Street south of Main St) closed through spring

253rd Avenue access

  • The frontage road access onto Highway 169 north of 253rd Avenue is permanently closed. Traffic will exit and enter via 253rd Avenue.

255th Avenue access

257th Avenue access

  • 257th Avenue will now access Highway 169 via 121st Street, directly across from 255th Avenue.

269th Avenue will remain closed through the spring

Project email/text updates

Sign me up!

Contact Us


Project Email & Hotline

[email protected]

(763) 463-7818

 

Business Liaison

[email protected]

(763) 248-1697