The City of International Falls is improving 9th Street from 14th Avenue to Highway 53. The proposed improvements include:
- Addition of a multi-use path along the north side of the corridor
- New concrete curb and gutter and roadway pavement
- Water main, storm sewer and sanitary sewer replacements
- Lead service line replacement
Project Updates: Oct. 27, 2025
Completed work
- Finished the following work on 9th Avenue from 11th Avenue to 8th Avenue:
- Sub-cutting
- Gravel placement
- Curb and gutter installation
- Paving the first layer of pavement
Upcoming work
- Finish paving from 11th Avenue to 8th Avenue.
- Begin lead service line replacement from curb to water meter from 11th Avenue to 8th Avenue. This will require work authorization from property owners.
CONTACTS
Dean Helstrom, P.E., Project Manager
Dean.Helstrom@bolton-menk.com
218-830-0856
Jason Fisher, P.E., City Engineer
Jason.Fisher@bolton-menk.com
218-600-6827
Casey Witzman, Onsite Representative & Lead Service Line Investigation
Casey.Witzman@bolton-menk.com
507-594-0518