9th Street Utility and Street Improvements
Project Overview
The City of International Falls is improving 9th Street from 14th Avenue to Highway 53. The proposed improvements include:
- Addition of a multi-use path along the north side of the corridor
- New concrete curb and gutter and roadway pavement
- Water main, storm sewer and sanitary sewer replacements
- Lead service line replacement
June 19, 2026
Work completed this week
- Water shutoff on the 500 block of 9th Street.
- Watermain work under Highway 53.
- Storm sewer installations in the 8th Avenue and 7th Avenue intersections.
- Water and sanitary service line replacement on 600 block of 9th Street.
Work planned for next week
- Storm sewer installation in the 6th Avenue intersection.
- Install light pole foundation and electrical work from 8th Avenue to 14th Avenue.
- Turf restoration on the south side of 9th Street from 8th Avenue to 11th Avenue.
- Lead water service replacements at various locations on 5th Street. Affected property owners have been notified.

Documents and Resources

July 29, 2025 Neighborhood Meeting invite
Grant Information
Grant Agreement No. 1060270, S.A.P. 134-594-001, Local Road Improvement Program (LRIP), Reconstruction of 9th Street from 3rd Avenue to 14th Avenue
Agency Leadership: Betty Bergstrom, City Administrator, 218-283-7983, [email protected]
Grant Manager: Mike Wallace, Interim Public Works Director, 218-283-4403, [email protected]
CONTACTS
Jordan Bauch
Onsite Project Representative and Lead Service Line Investigation
[email protected]
218-830-8176
Dean Helstrom, P.E., Project Manager
[email protected]
218-830-0856
Jason Fisher, P.E., City Engineer
[email protected]
218-600-6827