International Falls

2025 - 2026 Construction Projects

9th Street Utility and Street Improvements

Project Overview

The City of International Falls is improving 9th Street from 14th Avenue to Highway 53. The proposed improvements include:

  • Addition of a multi-use path along the north side of the corridor
  • New concrete curb and gutter and roadway pavement
  • Water main, storm sewer and sanitary sewer replacements
  • Lead service line replacement
May 29, 2026

Work completed this week

  • Sanitary sewer was installed on the 700 block of 9th Street and connected to the previously installed sanitary sewer on the 800 block of 9th Street.
  • About half of the water and sanitary sewer services have been connected to the water and sanitary mains on the 700 block of 9th Street.
  • Temporary water has passed testing from 5th Avenue to Highway 53.

Work planned for next week

  • Continue replacing water and sanitary sewer services on the 700 Block of 9th street along with 4 services on the west end of the 600 block of 9th Street.
  • Install storm sewer in in the 8th and 7th Avenue intersections.
  • Potentially switch residents over to temporary water from 5th Avenue to Highway 53.

Documents and Resources

9th Street Construction Meeting Notice

July 29, 2025 Neighborhood Meeting invite

Temporary Water Notice

What’s Under My Street Video

Grant Information

Grant Agreement No. 1060270, S.A.P. 134-594-001, Local Road Improvement Program (LRIP), Reconstruction of 9th Street from 3rd Avenue to 14th Avenue

Agency Leadership: Betty Bergstrom, City Administrator, 218-283-7983, [email protected]

Grant Manager: Mike Wallace, Interim Public Works Director, 218-283-4403, [email protected]

CONTACTS

Jordan Bauch
Onsite Project Representative and Lead Service Line Investigation
[email protected]
218-830-8176

Dean Helstrom, P.E., Project Manager
[email protected]
218-830-0856

Jason Fisher, P.E., City Engineer
[email protected]
218-600-6827