9th Street Utility and Street Improvements
Project Overview
The City of International Falls is improving 9th Street from 14th Avenue to Highway 53. The proposed improvements include:
- Addition of a multi-use path along the north side of the corridor
- New concrete curb and gutter and roadway pavement
- Water main, storm sewer and sanitary sewer replacements
- Lead service line replacement
July 17, 2026
Work completed this week
- Curb and gutter installations from 8th Avenue to 6th Avenue.
- Water main installations on 9th Street from 5th Avenue to 4th Avenue.
Work planned for next week
- Hydrant relocation at the 6th Avenue / 9th Street intersection
- Install curb and gutter from 8th Avenue to 6th Avenue.
- Install sewer on 9th Street from 5th Avenue to 4th Avenue.
- Sub cut and gravel placement on 500 block.
- Install sewer and water services on 400 block.

Documents and Resources

July 29, 2025 Neighborhood Meeting invite
Grant Information
Grant Agreement No. 1060270, S.A.P. 134-594-001, Local Road Improvement Program (LRIP), Reconstruction of 9th Street from 3rd Avenue to 14th Avenue
Agency Leadership: Betty Bergstrom, City Administrator, 218-283-7983, [email protected]
Grant Manager: Mike Wallace, Interim Public Works Director, 218-283-4403, [email protected]
CONTACTS
Jordan Bauch
Onsite Project Representative and Lead Service Line Investigation
[email protected]
218-830-8176
Dean Helstrom, P.E., Project Manager
[email protected]
218-830-0856
Jason Fisher, P.E., City Engineer
[email protected]
218-600-6827