2025 - 2026 Construction Projects

9th Street Utility and Street Improvements

Project Overview

The City of International Falls is improving 9th Street from 14th Avenue to Highway 53. The proposed improvements include:

  • Addition of a multi-use path along the north side of the corridor
  • New concrete curb and gutter and roadway pavement
  • Water main, storm sewer and sanitary sewer replacements
  • Lead service line replacement

Project Updates: Nov. 10, 2025

Completed work
  • Continued replacing lead service lines.
  • Began curb stop adjustments, trail gravel placement and general restoration and clean-up work.
Upcoming work
  • Continue lead service line replacement from curb to water meter from 10th Avenue to 9th Avenue. This will require work authorization from property owners.
  • Continue curb stop adjustments, trail gravel placement and general restoration and clean-up work.
Click image to view larger version.

CONTACTS

Dean Helstrom, P.E., Project Manager
Dean.Helstrom@bolton-menk.com
218-830-0856

Jason Fisher, P.E., City Engineer
Jason.Fisher@bolton-menk.com
218-600-6827

Casey Witzman, Onsite Representative & Lead Service Line Investigation
Casey.Witzman@bolton-menk.com
507-594-0518