International Falls

2025 - 2026 Construction Projects

9th Street Utility and Street Improvements

Project Overview

The City of International Falls is improving 9th Street from 14th Avenue to Highway 53. The proposed improvements include:

  • Addition of a multi-use path along the north side of the corridor
  • New concrete curb and gutter and roadway pavement
  • Water main, storm sewer and sanitary sewer replacements
  • Lead service line replacement

 

July 17, 2026

Work completed this week

  • Curb and gutter installations from 8th Avenue to 6th Avenue.
  • Water main installations on 9th Street from 5th Avenue to 4th Avenue.

Work planned for next week

  • Hydrant relocation at the 6th Avenue / 9th Street intersection
  • Install curb and gutter from 8th Avenue to 6th Avenue.
  • Install sewer on 9th Street from 5th Avenue to 4th Avenue.
  • Sub cut and gravel placement on 500 block.
  • Install sewer and water services on 400 block.
Click image to view larger version.

Documents and Resources

9th Street Construction Meeting Notice

July 29, 2025 Neighborhood Meeting invite

Temporary Water Notice

What’s Under My Street Video

Grant Information

Grant Agreement No. 1060270, S.A.P. 134-594-001, Local Road Improvement Program (LRIP), Reconstruction of 9th Street from 3rd Avenue to 14th Avenue

Agency Leadership: Betty Bergstrom, City Administrator, 218-283-7983, [email protected]

Grant Manager: Mike Wallace, Interim Public Works Director, 218-283-4403, [email protected]

CONTACTS

Jordan Bauch
Onsite Project Representative and Lead Service Line Investigation
[email protected]
218-830-8176

Dean Helstrom, P.E., Project Manager
[email protected]
218-830-0856

Jason Fisher, P.E., City Engineer
[email protected]
218-600-6827