2025 - 2026 Construction Projects

Stenberg Addition and 14th Street Mill and Overlay Improvements

Project Overview

The City of International Falls is improving:

  • 14th Street
  • 16th Street
  • 17th Street
  • 18th Street
  • 15th Avenue
  • 13th Avenue

These roads are proposed for mill and overlay work, which is the least invasive and time-consuming process of repaving roads. Only the top layer of pavement is replaced to provide a new surface for vehicles to drive on.

Project Updates: Sept. 12, 2025

Completed work
  • Formed driveway aprons in front of the ambulance and fire station and the stoop at the library.
  • Milled and replaced miscellaneous curb & gutter in Stenberg addition and on 14th Street.
Upcoming work

City Hall and Library

  • Preparing and paving both parking lots.
  • Finish concrete work in front of library.

Stenberg Addition and 14th Street

  • Continue replacing damaged curb & gutter.
  • Paving work.

CONTACTS

Dean Helstrom, P.E., Project Manager
Dean.Helstrom@bolton-menk.com
218-830-0856

Jason Fisher, P.E., City Engineer
Jason.Fisher@bolton-menk.com
218-600-6827

Casey Witzman, Onsite Representative & Lead Service Line Investigation
Casey.Witzman@bolton-menk.com
507-594-0518