Project Updates – Oct. 14, 2025

Completed work this past week

  • Graded the roads in preparation for paving.
  • Expanded the Martindale Street cul-de-sac.
  • Paved the first layer of road pavement and curb on Henning Circle and Hickory Lane today, Oct. 14.

Upcoming work

  • Due to the rain, paving on Martindale Street is tentatively rescheduled for tomorrow, Oct. 15, weather permitting.
    • Please drive cautiously through the area during this work; a number of trucks will be driving in and out of the project site.
    • There will only be one lane of access at a time to protect the newly installed pavement. Access should generally be maintained during this process, but there may short delays while work occurs in front of your driveway.
  • Final storm sewer work will be completed later this week or next week.
  • Restoration work is tentatively scheduled for later this week and next week.
  • Final paving will be scheduled after restoration work is completed.
  • To facilitate construction, some resident mailboxes may need to be temporarily removed. Property owners will be notified in advance if this is necessary.