Phase 1 Construction Updates
May 28, 2026
Road Closure
The Fremont Ave road closure and detour is active. The Road will remain open to local traffic, though temporary restrictions may occur during active construction. All traffic on Northwood Road should enter and exit the neighborhood from the south to avoid delays and construction activity.
Safety Reminder
Please remain spatially aware and cautious in and around construction areas and equipment. Drive slowly in construction areas, make sure you are visible to equipment operators, and comply with any verbal instructions from workers on-site. Thank you for your patience and understanding during construction!
Island View Road & Island Circle (Reconstruction Areas)
Week of May 25
- The contractor continued installing storm sewer on Island View Road.
- Crews continued installing sanitary sewer and water services on the north end of Island View Road.
- Vehicle access to affected residences on Island View Rd will not be available from 7 a.m. to 7 p.m. during utility work. Utility work will be a moving operation, and crew locations will progress throughout the day. Please park vehicles outside of the project area during construction. Access will be restored by the end of each workday.
Week of June 1
- Early in the week, crews will be potholing (digging small holes to locate underground utilities) between 15906 Island View Rd and 15764 Island View Road (see map below)
- During these activities, all residents on Island Circle and Island View Road south of 15906 Island View Road will need to enter and exit the project area from the south.
- Residents between 15906 Island View Road and 15764 Island View Road will not have access to driveways during the workday, from 7 a.m. to 7 p.m.
- Please park vehicles on the north end of Island View Road outside of the reconstruction area, and abide by any “No Parking” signs.
Island View Circle (Reconstruction Area)
Week of May 25
- No major construction work occurred this week on Island View Circle.
- Vehicle access will be available while no construction work is occurring.
Week of June 1
- Crews will be resuming underground utility work on Island View Circle next week, starting Monday. Vehicle access will not be available for residences on Island View Cir during the workday, from 7 a.m. to 7 p.m.
- Please park vehicles outside of the project area during construction. Island View Cir residents are encouraged to park along Northwood Rd NW near the intersection with Island View Rd.
- Parking availability is expected to increase as work progresses on Island View Rd.
- Residents with vehicles parked inside the vehicle access closure area will be allowed to park on-street just west of 3715 Island View Cir, to reduce walking distance to cars parked outside of the closure area.
- Residents should park all vehicles on the north side of Island View Cir, and maintain space for others to drive in the area.
- Residents may use golf carts, bikes, or other small personal vehicles to reduce walking distance to vehicles parked outside the work area.
- Vehicle access will be restored by 7 p.m. on work days and all day on weekends.
- Upcoming construction work and vehicle access restrictions will be communicated in future email updates.
Fremont Avenue (Reclaim and Mill & Overlay Areas)
Week of May 25
- Crews continued concrete curb, driveway, and sidewalk installations on the west side of Fremont Avenue.
- The contractor conducted spot concrete installations throughout the project area.
- Please check your door for property-specific notices.
Week of June 1
- Crews will continue concrete curb, driveway, and sidewalk installations on the west side of Fremont Ave.
- Spot concrete installations will continue throughout the project area.
Remaining Reclamation Areas
(East end of Knollridge Drive, Viewcrest Circle, Visionary Heights Circle, East end of Hawk Ridge Road, Lake Haven Court, Shady Cove Point, Fremont Street, Fremont Circle, Crystal Circle, and the North end of Island View Road)
Week of May 25
- The contractor completed wear course paving on select streets in coordination with paving of mill and overlay streets. This includes the east end of Knollridge Drive and the east end of Hawk Ridge Road, which was paved today, Thursday May 28.
Week of June 1
- No substantial work is anticipated in reclamation areas this week.
Remaining Mill & Overlay Areas
(Linden Circle, Knollridge Court, Knollridge Drive, Hawk Ridge Court, Hawk Ridge Road, Tahinka Court, and Tahinka Place)
Week of May 25
- Texas underseal (a layer of oil sealant and pea gravel) was installed on Tuesday, May 26 in preparation for wear course paving.
- Wear course pavement was installed on Tahinka Ct, Tahinka Pl, Knollridge Ct, and Hawk Ridge Ct on Wednesday, May 27.
- Wear course paving finished today, (Thursday, May 28) with Knollridge Drive, Hawk Ridge Road, and Linden Cir.
Week of June 1
- No substantial work is anticipated in mill and overlay areas this week.
Access, Parking & Deliveries
- Access to homes will be maintained whenever possible.
- When driveways are impacted, crews will coordinate directly with residents. Please look for notices delivered to your door.
- If access is temporarily unavailable, residents will be asked to park on adjacent streets during work hours. This will be communicated in advance. Onsite project staff will be available to assist where possible.
- Temporary mailboxes for impacted properties have been coordinated with USPS.
- For residences on Island View Rd NW north of the Island Cir Intersection: Temporary mailbox hub located at the corner of 15645 Fremont Avenue NW
- For residences on Island View Cir, Island Cir, and Island View Rd south of Island Cir: Temporary mailbox hub located at the corner of 16000 Northwood Rd NW
- For residences on Fremont Ave north of Crystal Cir (15616 to 15710): Temporary mailbox hub located at the end of the cul-de-sac on Crystal Cir NW.
- For residences on Fremont Ave south of Crystal Cir and north of Fremont Cir (15770 to 15820): Temporary mailbox hub located at the end of the cul-de-sac on Fremont Cir NW.
- For residences located in Fremont St NW (3344 to 3386): Mailboxes will be moved from Fremont Ave on to Fremont St NW.
- For residences south of Fremont St and North of Arctic Cir (15960 to 15990): Temporary mailbox hub located south of Arctic Cir NW on the west side of the road.
Contact Us
For general questions, concerns, or to be directed to the right contact, please reach out to: [email protected] or (952) 373-0176.
The City of Prior Lake and their consultant, Bolton & Menk, will also have staff onsite during construction who can assist with questions and general access needs.
Thank you for your cooperation as we complete these important infrastructure improvements. We appreciate your patience as we work to improve the Northwood Road area.
May 21, 2026
View May 22, 2026 Update
Island View Road & Island Circle (Reconstruction Areas)
Week of May 18
- The contractor continued installing underground sanitary sewer and water services on Island View Rd.
- Crews began installing storm sewer on Island View Rd.
- Crews began street building operations at the intersection of Island View Road and Island View Circle, and are moving north.
- Vehicle access to affected residences on Island View Rd will not be available from 7 a.m. to 7 p.m. during utility work. Utility work will be a moving operation, and crew locations will progress throughout the day. Please park vehicles outside of the project area during construction. Access will be restored by the end of each workday.
Week of May 25
- No construction work will occur on Memorial Day.
- Crews will continue installing sanitary sewer and water services on the north end of Island View Rd.
- Crews will continue storm sewer installations on Island View Rd and Island Cir.
- Crews will continue road building operations as underground work is completed, generally moving north.
- Vehicle access to affected residences on Island View Rd will not be available from 7 a.m. to 7 p.m. during utility work.
Island View Circle (Reconstruction Area)
Week of May 18
- Crews continued underground sanitary sewer and watermain work on Island View Cir.
- Vehicle access will not be available for residences on Island View Cir during the workday, from 7 a.m. to 7 p.m.
- Please park vehicles outside of the project area during construction. Island View Cir residents are encouraged to park along Northwood Rd NW near the intersection with Island View Rd.
- Parking availability is expected to increase as street building progresses on Island View Rd in coming weeks.
- Residents with vehicles parked inside the vehicle access closure area will be allowed to park on-street just west of 3715 Island View Cir, to reduce walking distance to cars parked outside of the closure area.
- Residents should park all vehicles on the north side of Island View Cir, and maintain space for others to drive in the area.
- Residents may use golf carts, bikes, or other small personal vehicles to reduce walking distance to vehicles parked outside the work area.
- Vehicle access will be restored by 7 p.m. on work days and all day on weekends.
Week of May 25
- No construction work will occur on Memorial Day.
- No major construction operations are anticipated on Island View Circle this week.
- Vehicle access to driveways will be available for Island View Cir Residences starting the week of May 25. Access will remain open until underground utility work resumes. Please monitor future construction updates for information on future vehicle access restrictions.
Fremont Avenue (Reclaim and Mill & Overlay Areas)
Week of May 18
- Crews continued concrete curb, driveway, and sidewalk installations on the west side of Fremont Avenue.
- MVEC continued installing a new electric utility line along Fremont Ave from CR 82 going south and continuing along Northwood Road to the south of the project area.
- Gigapower began utility work on the north section of Fremont Avenue.
Week of May 25
- No construction work will occur on Memorial Day.
- Crews will continue concrete curb, driveway, and sidewalk installations on the west side of Fremont Avenue.
- The contractor will conduct spot concrete installations throughout the project area.
Remaining Reclamation Areas
(East end of Knollridge Drive, Viewcrest Circle, Visionary Heights Circle, East end of Hawk Ridge Road, Lake Haven Court, Shady Cove Point, Fremont Street, Fremont Circle, Crystal Circle, and the North end of Island View Road)
Week of May 18
- Crews began installing manhole castings and raising gate valves in preparation for wear course paving.
- The contractor installed wear course paving in the following areas on May 21 (see map):
- Visionary Heights Circle
- View Crest Circle
- Lake Haven Court
- Shady Cove Point
Week of May 25
- No construction work will occur on Memorial Day.
- The contractor will complete wear course paving on select streets on Tuesday, May 26 and Wednesday, May 27 in coordination with paving of mill and overlay streets (weather dependent, See full details below). This will include the east end of Knollridge Drive and the east end of Hawk Ridge Road.
- No on-street parking will be allowed during paving operations. Please follow all posted “No Parking” signs, as these signs will indicate when crews will begin paving each street.
- Driveways will generally be accessible except for the approximately 30-60 minute window when crews are paving directly in front of your residence. If you need to leave your residence at a specific time and cannot afford delays, please park on nearby streets outside of the paving area.
-
Access to Northwood Road will be available at all times, from one direction or the other, through one of Knollridge Dr NW or Hawk Ridge Rd NW.
Remaining Mill & Overlay Areas
(Linden Circle, Knollridge Court, Knollridge Drive, Hawk Ridge Court, Hawk Ridge Road, Tahinka Court, and Tahinka Place)
Week of May 18
- The contractor conducted repairs to base pavement as-needed in preparation for wear course paving.
- Texas underseal (a layer of oil sealant and pea gravel) will be installed on Friday, May 22 (weather dependent) for Mill and Overlay areas.
- No on-street parking will be allowed starting at 7:00 a.m. on Mill and Overlay streets. Affected residences have been notified.
- Loose pea gravel will remain over the weekend, and will be swept up early next week prior to paving operations. Please drive slowly in work areas.
Week of May 25
- No construction work will occur on Memorial Day.
- The contractor will complete wear course paving on the following streets on Tuesday, May 26 and Wednesday, May 27 (weather dependent) (See map below):
- Linden Circle
- Tahinka Court
- Tahinka Place
- Knollridge Drive
- Knollridge Court
- Hawk Ridge Road
- Hawk Ridge Court
- No on-street parking will be allowed during paving operations. Please follow all posted “No Parking” signs, as these signs will indicate when crews will begin paving each street.
- Driveways will generally be accessible except for the approximately 30-60 minute window when crews are paving directly in front of your residence. If you need to leave your residence at a specific time and cannot afford delays, please park on nearby streets outside of the paving area.
-
Access to Northwood Road will be available at all times, from one direction or the other, through one of Knollridge Dr NW or Hawk Ridge Rd NW.
May 26 & 27 Paving Map
May 14, 2026
View May 14, 2026 Update
Road Closure
- The Fremont Ave road closure and detour is active. The Road will remain open to local traffic, though temporary restrictions may occur during active construction. All traffic on Northwood Road should enter and exit the neighborhood from the south to avoid delays and construction activity.
Safety Reminder
- Please remain spatially aware and cautious in and around construction areas and equipment. Drive slowly in construction areas, make sure you are visible to equipment operators, and comply with any verbal instructions from workers on-site. Thank you for your patience and understanding during construction!
Island View Road & Island Circle (Reconstruction Areas)
Week of May 11
- Two crews continued installing underground utilities on Island View Rd and Island Cir this week.
- Crews completed sanitary sewer service installations this week, and will begin work on water services later in the week.
- Crews may start road building operations at the south end of Island View Road later in the week, and continue next week.
- CenterPoint continued gas utility replacements.
- Vehicle access to affected residences on Island View Rd will not be available from 7 a.m. to 7 p.m. during utility work. Utility work will be a moving operation, and crew locations will progress throughout the day. Please park vehicles outside of the project area during construction. Access will be restored by the end of each workday.
Week of May 18
- Crews will continue watermain work on Island View Rd, generally moving north.
- Crews will continue road building operations as watermain work is completed, generally moving north.
- Vehicle access to affected residences on Island View Rd will not be available from 7 a.m. to 7 p.m. during utility work.
- CenterPoint will wrap up remaining gas utility replacements.
Island View Circle (Reconstruction Area)
Week of May 11
- Crews continued underground sanitary sewer and watermain work on Island View Cir.
- Vehicle access will not be available for residences on Island View Cir during the workday, from 7 a.m. to 7 p.m.
- Please park vehicles outside of the project area during construction. Island View Cir residents are encouraged to park along Northwood Rd NW near the intersection with Island View Rd.
- Parking availability is expected to increase as work progresses on Island View Rd in coming weeks.
- Residents with vehicles parked inside the vehicle access closure area will be allowed to park on-street just west of 3715 Island View Cir, to reduce walking distance to cars parked outside of the closure area.
- Residents should park all vehicles on the north side of Island View Cir, and maintain space for others to drive in the area.
- Residents may use golf carts, bikes, or other small personal vehicles to reduce walking distance to vehicles parked outside the work area.
- Vehicle access will be restored by 7 p.m. on work days and all day on weekends.
- CenterPoint continued gas utility replacements.
Week of May 18
- Crews will continue underground sanitary sewer and watermain work on Island View Cir.
- Vehicle access will not be available for residences on Island View Cir during the workday, from 7 a.m. to 7 p.m. Parking and access arrangements will continue the same as the previous week.
- CenterPoint will continue gas utility replacements.
Fremont Avenue (Reclaim and Mill & Overlay Areas)
Week of May 11
- Crews continued grading, and concrete work will begin on the west side of Fremont Avenue. Notices will be posted on the front doors of affected residences with more information.
- Milling the top layer of pavement in the north section of Fremont Avenue has been delayed for the time being.
- MVEC continued installing a new electric utility line along Fremont Ave from CR 82 going south and continuing along Northwood Road to the south of the project area.
- Gigapower began utility work on the north section of Fremont Avenue.
Week of May 18
- Crews will continue grading and concrete work on the west side of Fremont Avenue.
- Gigapower will continue utility work on the north section of Fremont Avenue.
- MVEC will continue installing a new electric utility line along Fremont Ave from CR 82 going south and continuing along Northwood Road to the south of the project area.
Remaining Reclamation Areas
(East end of Knollridge Drive, Viewcrest Circle, Visionary Heights Circle, East end of Hawk Ridge Road, Lake Haven Court, Shady Cove Point, Fremont Street, Fremont Circle, Crystal Circle, and the North end of Island View Road)
Week of May 11
- The contractor finished reclaiming pavement on affected streets.
- The contractor installed base pavement in the following areas on Wednesday, May 13 (see map):
- Hawk Ridge Road from 2983 Hawk Ridge Rd to the intersection with Northwood Rd
- Knollridge Drive from 3027 Knollridge Drive to the intersection with Northwood Rd
- Viewcrest Circle
- Visionary Heights Circle
- Lake Haven Court
- Shady Cove Point
- Vehicle access will generally be available now that base paving has been completed.
Week of May 18
- Crews will begin installing manhole castings and raising gate valves in preparation for wear course paving.
Remaining Mill & Overlay Areas
(Linden Circle, Knollridge Court, Knollridge Drive, Hawk Ridge Court, Hawk Ridge Road, Tahinka Court, and Tahinka Place)
Week of May 11
- The contractor continued spot concrete curb and sidewalk replacements and ADA pedestrian ramp improvements on select streets. See updated map of affected streets.
- Crews will complete milling operations (removing the top layer of pavement for replacement) late this week or early next week.
- Vehicle access will be limited during milling operations at the work location, but access will be maintained from one direction or the other. Outside of this work, vehicle access will generally be available.
Week of May 18
- Crews will complete milling operations early in the week.
May 7, 2026
Click to View May 7, 2026 Update
Road Closure
- The Fremont Ave road closure and detour is active. The Road will remain open to local traffic, though temporary restrictions may occur during active construction. Other streets will be closed as construction progresses to those areas, as noted below. Your access may need to change from day to day, including coming from the opposite direction. All traffic on Northwood Road should enter and exit the neighborhood from the south to avoid delays and construction activity.
Island View Road & Island Circle (Reconstruction Areas)
Week of May 4
- Two crews continued installing underground utilities on Island View Rd and Island Cir this week.
- CenterPoint continued gas utility replacements.
Week of May 11
- Crews will continue watermain and sanitary sewer work on Island View Rd, generally moving north.
- Vehicle access to affected residences on Island View Rd will not be available from 7 a.m. to 7 p.m. during utility work between the two crews’ work locations. Utility work will be a moving operation, and crew locations will progress throughout the day. Please park vehicles outside of the project area during construction. Access will be restored by the end of each workday.
- CenterPoint will continue gas utility replacements.
Island View Circle (Reconstruction Area)
Week of May 4
- The contractor completed watermain and sanitary sewer work this week, starting at the Island View Rd and Island View Cir intersection and moving east into Island View Cir.
- Crews will began reclaiming pavement on the western half of Island View Cir on May 7.
- Vehicle access will be available around construction activity during the day, but there may be occasional delays for 30 to 60 minutes due to construction.
- If timely vehicle access is needed for appointments or scheduled daily activities, we strongly recommend parking your vehicle outside of the construction area to ensure there are no delays in getting your vehicle to your destination.
- Vehicle access will continue to be restored by 7 p.m. on work days.
- Crews will continue striping pavement for reclaiming this week.
- Crews will begin constructing a temporary access street for upcoming utility work on Island View Cir.
- CenterPoint continued gas utility replacements.
Week of May 11
- Crews will begin underground utility work on Island View Cir, generally moving east.
- Vehicle access will be available around construction activity during the day, but there may be occasional delays for 30 to 60 minutes due to construction.
- If timely vehicle access is needed for appointments or scheduled daily activities, we strongly recommend parking your vehicle outside of the construction area to ensure there are no delays in getting your vehicle to your destination.
- Vehicle access will continue to be restored by 7 p.m. on work days.
- CenterPoint will continue gas utility replacements.
Fremont Avenue (Reclaim and Mill & Overlay Areas)
Week of May 4
- Crews continued with concrete removals and rough grading for the sidewalk on the west side of Fremont Avenue.
- Driveways have been ramped to allow vehicle access.
- An additional 4 feet of pavement on the west side of Fremont Avenue will be removed and reclaimed on May 7 to allow for additional space to complete curb work.
- MVEC continued installing a new electric utility line along Fremont Ave from CR 82 going south and continuing along Northwood Road.
- Gigapower began utility work on the north section of Fremont Avenue.
Week of May 11
- Crews will continue grading and concrete work on the west side of Fremont Avenue.
- Gigapower will continue utility work on the north section of Fremont Avenue.
- MVEC will continue installing a new electric utility line along Fremont Ave from CR 82 going south and continuing along Northwood Road to the south of the project area.
Remaining Reclamation Areas
(East end of Knollridge Drive, Viewcrest Circle, Visionary Heights Circle, East end of Hawk Ridge Road, Lake Haven Court, Shady Cove Point, Fremont Street, Fremont Circle, Crystal Circle, and the North end of Island View Road)
Week of May 4
- The contractor continued concrete curb and sidewalk replacement and ADA ramp improvement work.
- Crews began reclaiming pavement on affected streets.
- Vehicle access will be limited during pavement reclamation at the work location, but access will be maintained from one direction or the other. Outside of this work, vehicle access will generally be available. If concrete work will impact driveway access, residents will be notified of what to expect.
- No work will occur on Lake Bluff Cir. See updated map of affected streets
Week of May 11
- The contractor will finish reclaiming pavement on affected streets.
- Crews will begin milling and paving operations sometime mid-week. Future updates will be provided regarding this work.
- Vehicle access will be limited during paving operations at the work location, but access will be maintained from one direction or the other. Outside of this work, vehicle access will generally be available.
Remaining Mill & Overlay Areas
(Linden Circle, Knollridge Court, Knollridge Drive, Hawk Ridge Court, Hawk Ridge Road, Tahinka Court, and Tahinka Place)
Week of May 4
- The contractor continued spot concrete curb and sidewalk replacements and ADA pedestrian ramp improvements on select streets. See updated map of affected streets.
Week of May 11
- Crews will begin milling and paving operations sometime mid-week. Future updates will be provided regarding this work.
- Vehicle access will be limited during milling operations at the work location, but access will be maintained from one direction or the other. Outside of this work, vehicle access will generally be available.
April 30, 2026
Click to View April 30, 2026 Update
Road Closure
- The Fremont Ave road closure and detour is active. The Road will remain open to local traffic, though temporary restrictions may occur during active construction. Other streets will be closed as construction progresses to those areas, as noted below. Your access may need to change from day to day, including coming from the opposite direction. All traffic on Northwood Road should enter and exit the neighborhood from the south to avoid delays and construction activity.
Island View Road & Island Circle (Reconstruction Areas)
Week of April 27
- A temporary water shutoff occured on Tuesday, April 28 to perform work necessary to connect affected residences to temporary water and begin watermain utility work.
- If you are not connected to temporary water or experience disruptions in water service during construction, please contact the project email or phone hotline.
- Two crews began utility work on Island View Road on April 29.
- One crew began watermain work starting at the Island Cir intersection and moving north.
- A second crew began installing sanitary sewer starting at the intersection of Island View Rd and Island View Cir, moving east to Island View Cir.
- Once this work is complete, this crew will continue sanitary sewer work starting at the intersection of Island View Cir and Island View Rd, and moving north on Island View Rd.
- Vehicle access to affected residences on Island View Rd will not be available from 7 a.m. to 7 p.m. during utility work, between the two crews’ work locations. Utility work will be a moving operation, and crew locations will progress throughout the day. Please park vehicles outside of the project area during construction. Access will be restored by the end of each workday.
- CenterPoint continued gas utility replacements.
Week of May 4
- Crews will continue watermain and sanitary sewer work on Island View Rd, generally moving north.
- CenterPoint will continue gas utility replacements.
Island View Circle (Reconstruction Area)
Week of April 27
- A temporary water shutoff occured on Tuesday, April 28 to perform work necessary to connect affected residences to temporary water and begin watermain utility work.
- Crews continued connecting additional affected residences to temporary water this week.
- If you are not connected to temporary water or experience disruptions in water service during construction, please contact the project email or phone hotline.
- The contractor began watermain and sanitary sewer work this week, starting at the Island View Rd and Island View Cir intersection and moving east into Island View Cir.
- Vehicle access to affected residences on Island View Cir will not be available from 7 a.m. to 7 p.m. this week. Please park vehicles outside of the project area during construction. Access will be restored by the end of each workday.
- Once this work is complete, vehicle access will generally be available for Island View Cir for the time being.
- CenterPoint continued gas utility replacements.
Week of May 4
- Vehicle access will generally be available next week on Island View Cir once initial water main and sanitary sewer work is completed in the intersection.
- The contractor expects to begin reclaiming pavement for utility construction in approximately 2-3 weeks.
- CenterPoint will continue gas utility replacements.
Fremont Avenue (Reclaim and Mill & Overlay Areas)
Week of April 27
- Crews began reclaiming 8 feet of pavement on the west side of Fremont Avenue on April 30. Curb and driveway removals and stripping topsoil will follow reclamation work. Driveways will be ramped to provide access until the contractor completes concrete work in the future.
- If you have any private features or landscaping in the public right-of-way that you would like to save, please salvage these items.
- MVEC continued installing a new electric utility line along Fremont Ave from CR 82 going south and continuing along Northwood Road.
- Residences on the west side of Fremont Avenue will be switched temporary mailboxes starting April 30.
- Impacted residences will be notified of the relocated mailbox and service transition. Please regularly check front doors for door hangers with more information.
- For residences north of Crystal Cir (15616 to 15710): Temporary mailbox hub located at the end of the cul-de-sac on Crystal Cir NW.
- For residences south of Crystal Cir and north of Fremont Cir (15770 to 15820): Temporary mailbox hub located at the end of the cul-de-sac on Fremont Cir NW.
- For residences located in Fremont St NW (3344 to 3386): Mailboxes will be moved from Fremont Ave on to Fremont St NW.
- For residences south of Fremont St and North of Arctic Cir (15960 to 15990): Temporary mailbox hub located south of Arctic Cir NW on the west side of the road.
Week of May 4
- Gigapower will begin utility work on the north section of Fremont Avenue.
- MVEC will continue installing a new electric utility line along Fremont Ave from CR 82 going south and continuing along Northwood Road to the south of the project area.
Remaining Reclamation Areas
(East end of Knollridge Drive, Viewcrest Circle, Visionary Heights Circle, East end of Hawk Ridge Road, Lake Haven Court, Shady Cove Point, Fremont Street, Fremont Circle, Crystal Circle, and the North end of Island View Road)
Week of April 27
- The contractor began spot concrete curb and sidewalk replacement and ADA ramp improvement work on select streets.
- No work will occur on Lake Bluff Cir. See updated map of affected streets
Week of May 4
- Once the contractor completes curb and sidewalk replacement and ADA ramp improvement work, they will begin reclaiming pavement on affected streets.
- The majority of this work will be completed within approximately one month.
- Vehicle access will be limited during pavement reclamation at the work location, but access will be maintained from one direction or the other. Outside of this work, vehicle access will generally be available. If concrete work will impact driveway access, residents will be notified of what to expect.
Remaining Mill & Overlay Areas
(Linden Circle, Knollridge Court, Knollridge Drive, Hawk Ridge Court, Hawk Ridge Road, Tahinka Court, and Tahinka Place)
Week of April 27
- The contractor began spot concrete curb and sidewalk replacements and ADA pedestrian ramp improvements on select streets. This initial work will be completed in approximately 2 weeks, and pavement milling with not be completed at this time. See updated map of affected streets.
- Access to residences will generally be maintained during this work. If concrete work will impact driveway access, residents will be notified of what to expect.
Week of May 4
- The contractor will continue spot concrete curb and sidewalk replacements and ADA pedestrian ramp improvements on select streets.
April 24, 2026
Click to view April 24, 2026 Update
Road Closure
- The Fremont Ave road closure and detour is active. The Road will remain open to local traffic, though temporary restrictions may occur during active construction. Other streets will be closed as construction progresses to those areas, as noted below. Your access may need to change from day to day, including coming from the opposite direction. All traffic on Northwood Road should enter and exit the neighborhood from the south to avoid delays and construction activity.
Island View Road & Island Circle (Reconstruction Areas)
Week of April 20
- Additional tree removals were completed.
- Pavement reclaiming was completed in reconstruction areas. The contractor has graded the area to provide vehicle access.
- Curb and topsoil removals were completed.
- The contractor has set up temporary water system in anticipation of connecting residences to temporary water next week, which is required for watermain work. PVC piping was laid in boulevards, and temporary piping will be trenched through driveways to maintain access for homeowners.
- If your residence does not have any outdoor spigots connected to city water, contact the project email or phone hotline.
- CenterPoint continued gas utility replacements.
Week of April 27
- A temporary water shutoff will occur on Monday, April 27 at 9 a.m. to perform work necessary to connect affected residences to temporary water and begin watermain utility work. Affected residences will be notified prior to the water shutoff with a notice at your door.
- Water is expected to be back on by early to mid-afternoon for residences not connected to temporary water.
- The contractor will begin connecting temporary water at residences as early as 7 a.m. on Monday, a notice will be provided at your door if your residence is affected.
- There will be no access between the Northwood Road/Island View Road intersection and 15757 Island View Road starting at 8 a.m. on April 27, access will be restored by the end of the day. Access will be limited during working hours for the remainder of the week.
- The contractor will begin watermain and sanitary sewer work.
- Two separate crews will be working in the Island View Rd area, generally moving north. There will be no access between the two crews’ work areas during the workday.
- CenterPoint will continue gas utility replacements.
Island View Circle (Reconstruction Area)
Week of April 20
- Additional tree removals were completed.
- Pavement reclaiming was completed for approximately 300 feet of the western end of Island View Circle in order to accommodate utility installations.
- The contractor has set up temporary water system in anticipation of connecting residences to temporary water next week, which is required for watermain work. PVC piping was laid in boulevards, and temporary piping will be trenched through driveways to maintain access for homeowners.
- If your residence does not have any outdoor spigots connected to city water, contact the project email or phone hotline.
- Curb and topsoil removals were completed.
- CenterPoint continued gas utility replacements.
Week of April 27
- A temporary water shutoff will occur on Monday, April 27 at 9 a.m. to perform work necessary to connect affected residences to temporary water and begin watermain utility work. Affected residences will be notified prior to the water shutoff with a notice at your door.
- There will be no access Island View Cir starting at 8 a.m. on April 27, due to work on Island View Rd between Northwood Rd and 15757 Island View Rd. Access will be restored by the end of the day.
- Access will be limited during working hours for the remainder of the week as crews work to cross utilities towards Island View Circle.
- After this is completed, residences on Island View Circle will generally be accessible as crews progress north on Island View Road.
- The contractor will begin watermain and sanitary sewer work.
- CenterPoint will continue gas utility replacements.
Fremont Avenue (Reclaim and Mill & Overlay Areas)
Week of April 20
- Additional tree removals were completed.
- MVEC continued installing a new electric utility line along Fremont Ave from CR 82 going south and continuing along Northwood Road.
Week of April 27
- MVEC will continue installing a new electric utility line along Fremont Ave.
- The contractor will begin reclaiming 8 feet on the west side of Fremont Ave, tentatively planned to start on Wednesday, April 29. Removing curbs and stripping topsoil will follow after reclamation work. Driveways will be ramped to provide access until the contractor completes concrete work in the future.
Remaining Reclamation Areas
(East end of Knollridge Drive, Viewcrest Circle, Visionary Heights Circle, East end of Hawk Ridge Road, Lake Haven Court, Shady Cove Point, Lake Bluff, Circle, Fremont Street, Fremont Circle, Crystal Circle, and the North end of Island View Road)
Week of April 27
- The contractor will begin street reclamation, spot concrete curb and sidewalk replacement, and ADA ramp improvement work on select streets. The majority of this work will be completed in a one-month timeframe. See map of affected streets
- Access to residences will generally be maintained during this work. If concrete work will impact driveway access, residents will be notified of what to expect.
Remaining Mill & Overlay Areas
(Linden Circle, Knollridge Court, Knollridge Drive, Hawk Ridge Court, Hawk Ridge Road, Tahinka Court, and Tahinka Place)
Week of April 27
- The contractor will begin spot concrete curb and sidewalk replacements and ADA pedestrian ramp improvements on select streets. This initial work will be completed in approximately 2 weeks, and pavement milling with not be completed at this time. See map of affected streets.
- Access to residences will generally be maintained during this work. If concrete work will impact driveway access, residents will be notified of what to expect.
April 16, 2026
Click to view April 16, 2026 Update
Road Closure
- The Fremont Ave road closure has been put in place. The Road will remain open to local traffic, though temporary restrictions may occur during active construction. Other streets will be closed as construction progresses to those areas. Your access may need to change from day to day, including coming from the opposite direction. All traffic on Northwood Road should enter and exit the neighborhood from the south to avoid delays and construction activity.
Island View Road & Island Circle (Reconstruction Areas)
- Week of April 13
- Additional tree removals due to utility work impacts will take place on Friday, April 17. Residents who will have trees removed have been notified.
- Pavement reclaiming will take place on Friday, April 17. Expect delays and brief stretches where driveways will be inaccessible. All properties will be accessible at the end of the day.
- CenterPoint continued gas utility replacements.
- Week of April 20
- Saw cutting and driveway removals will take place. Once the driveway is removed the contractor will regrade the subbase (material underneath pavement) to provide access to homes.
- The contractor will begin setting up temporary water, which is required for watermain work. The contractor will lay PVC piping on the ground in boulevards. Temporary water piping will be trenched through driveways to maintain access for homeowners.
- The contractor will begin stripping topsoil and regrading the street in preparation for utility work.
- CenterPoint will continue gas utility replacements.
Island View Circle (Reconstruction Area)
- Week of April 13
- Additional tree removals due to utility work impacts will take place on Friday, April 17. Residents who will have trees removed have been notified.
- Pavement reclaiming will take place on Friday, April 17. Approximately 300 feet of the western end of Island View Circle will be reclaimed to accommodate utility installations. Expect delays and brief stretches where driveways will be inaccessible.
- Week of April 20
- Saw cutting and driveway removals will take place in areas that have been reclaimed. Once the driveway is removed the contractor will regrade the subbase (material underneath pavement) to provide access to homes.
- The contractor will begin setting up temporary water, which is required for watermain work. The contractor will lay PVC piping on the ground in boulevards. Temporary water piping will be trenched through driveways to maintain access for homeowners.
- The contractor will begin stripping topsoil and regrading the street in preparation for utility work.
Fremont Avenue (Reclaim and Mill & Overlay Areas)
- Week of April 13
- Additional tree removals due to utility work impacts will take place on Friday, April 17. Residents who will have trees removed have been notified.
- MVEC began installing a new electric utility line along Fremont Ave from CR 82 going south and continuing along Northwood Road.
- Week of April 20
- MVEC will continue installing a new electric utility line along Fremont Ave from CR 82 going south and continuing along Northwood Road.
Remaining Reclamation Areas
(East end of Knollridge Drive, Viewcrest Circle, Visionary Heights Circle, East end of Hawk Ridge Road, Lake Haven Court, Shady Cove Point, Lake Bluff, Circle, Fremont Street, Fremont Circle, Crystal Circle, and the North end of Island View Road)
- The contractor may begin storing construction materials in the center of select cul-de-sacs. Please use caution when traversing around stockpiles.
Remaining Mill & Overlay Areas
(Linden Circle, Knollridge Court, Knollridge Drive, Hawk Ridge Court, Hawk Ridge Road, Tahinka Court, and Tahinka Place)
- The contractor may begin storing construction materials in the center of select cul-de-sacs. Please use caution when traversing around stockpiles.
April 10, 2026
Click to view April 10, 2026 Update
Road Closure
- The Fremont Avenue road closure and associated detour will be put in place on Monday, April 13. The road will remain open to local traffic, though temporary restrictions may occur during active construction. Other streets will be closed as construction progresses to those areas. Your access may change during this time; future updates will detail these anticipated changes.
Island View Road & Island Circle (Reconstruction Areas)
- Week of April 6
- Tree stump grinding was completed for previously removed trees.
- Centerpoint Energy began gas facility replacements.
- Week of April 13
- The Contractor will begin to bring heavy equipment to site as well as have construction material deliveries dropped off. These will be placed along the sides of the streets and in the boulevards. Please take extra care when traveling through the area.
- Island View Road from just south of Island View Circle to approximately 15750 Island View Road and the entirety of Island Circle street pavement will be reclaimed either at the end of the week or early the week of April 20. Once the road has been reclaimed, more extensive construction activity will take place during the week of April 20. Please see future project updates for further information.
Island View Circle (Reconstruction Area)
- Week of April 6
- Tree stump grinding was completed for previously removed trees.
- Week of April 13
- The Contractor will begin to bring heavy equipment to site as well as have construction material deliveries dropped off. These will be placed along the sides of the streets and in the boulevards. Please take extra care when traveling through the area.
- Island View Circle will be reclaimed from the intersection with Island View Road to approximately 300-ft east at the end of the week or early the week of April 20 to accommodate initial utility installations on Island View Road. Please see future project updates for further information.
Fremont Avenue (Reclaim and Mill & Overlay Areas)
- Week of April 6
- No Activity
- Week of April 13
- The Contractor will begin to bring heavy equipment to site as well as have construction material deliveries dropped off. These will be placed along the sides of the streets and in the boulevards. Please take extra care when traveling through the area.
- The far western side (approximately 8-ft) of Fremont Avenue will be reclaimed to accommodate future planned concrete curb and sidewalk work (anticipated in May). Please see future project updates for further information. The road will remain traversable in a gravel-like condition.
- Private utility work will begin. MVEC will begin installing a new electric utility line along Fremont Ave from CR 82 going south and continuing along Northwood Road.
Remaining Reclamation Areas
(East end of Knollridge Drive, Viewcrest Circle, Visionary Heights Circle, East end of Hawk Ridge Road, Lake Haven Court, Shady Cove Point, Lake Bluff, Circle, Fremont Street, Fremont Circle, Crystal Circle, and the North end of Island View Road)
- No construction updates. Please continue to monitor future updates.
Remaining Mill & Overlay Areas
(Linden Circle, Knollridge Court, Knollridge Drive, Hawk Ridge Court, Hawk Ridge Road, Tahinka Court, and Tahinka Place)
- No construction updates. Please continue to monitor future updates.
April 1, 2026
Click to view April 1, 2026 Update
Construction for the Northwood Road Area Street & Utility Improvements Phase 1 project will begin soon. This email provides an overview of the anticipated schedule by work area, what to expect during construction, and how we will communicate with you throughout the project.
Anticipated Construction Schedule
Construction is expected to continue through fall 2026, with work progressing in phases and moving block by block to minimize impacts when possible. Please note that schedules are weather-dependent and may shift depending on construction scheduling, especially the reclamation and mill & overlay streets. Stay tuned for weekly updates that will detail scheduling updates once construction is underway.
Tree Clearing: Late March 2026
- Tree clearing was completed along the west side of Fremont Avenue for new sidewalk construction and select individual trees along Island View Road and Island View Circle that will be in conflict with utility construction (including utility services to homes).
- Additional individual tree removals may be required in the reconstruction areas during utility construction, depending on actual impacts. Tree removals will be avoided when possible.
Island View Road & Island Circle (Reconstruction Areas): Mid-April – Summer 2026
- Pavement removals
- Utility installation (sanitary sewer, watermain, storm sewer)
- Street reconstruction, curb installation, and driveway replacement approximately to the right-of-way
- Base asphalt paving, boulevard restoration, and final asphalt paving
Island View Circle (Reconstruction Area): Early May – Summer 2026
- Pavement removals
- Utility installation (sanitary sewer, watermain, storm sewer)
- Street reconstruction, curb installation, and driveway replacement (approximately to the right-of-way)
- Base asphalt paving, boulevard restoration, and final asphalt paving
Fremont Avenue (Reclaim and Mill & Overlay Areas): Late Spring – Summer 2026
- Pavement reclamation and removal of the west curb line from Northwood Road to Island View Road
- Storm sewer improvements
- Street grading, curb installation, sidewalk installation, and driveway replacement (on the west side approximately to the right-of-way)
- Base asphalt paving and boulevard restoration
- Pavement milling (north end) and final asphalt paving
Remaining Reclamation Areas: Summer 2026 (TBD)
(East end of Knollridge Drive, Viewcrest Circle, Visionary Heights Circle, East end of Hawk Ridge Road, Lake Haven Court, Shady Cove Point, Lake Bluff, Circle, Fremont Street, Fremont Circle, Crystal Circle, and the North end of Island View Road)
- Pavement reclamation, spot concrete curb/walk replacements, and ADA pedestrian ramp improvements
- Street grading and minor manhole improvements
- Base asphalt paving and boulevard restoration
- Final asphalt paving
Remaining Mill & Overlay Areas: Summer 2026 (TBD)
(Linden Circle, Knollridge Court, Knollridge Drive, Hawk Ridge Court, Hawk Ridge Road, Tahinka Court, and Tahinka Place)
- Pavement milling, spot concrete curb/walk replacements, and ADA pedestrian ramp improvements
- Base pavement repairs and minor manhole improvements
- Boulevard restoration and final asphalt paving
Note: The final asphalt paving will be completed together throughout all phases, where possible, and will likely be completed in late summer or fall.
What to Expect During Construction
You may notice the following activities as work progresses:
- Private utility work ahead of street construction by Communications, Gas, and Electric companies, including:
- CenterPoint gas facility replacements along Island View Road and Linden Circle
- MVEC electric line replacement along Northwood Road and Fremont Avenue
- Utility locate markings (colored flags and paint marks)
- Survey and construction staking in yards (wooden lath)
- Temporary water systems during watermain replacement in reconstruction areas (a notice will be delivered to your door if this applies to your property to have your temporary water service hooked up to your home)
- Noise, vibration, dust, and construction equipment in the area
- Crews working block by block with changing access
Access, Parking & Deliveries
- Access to homes will be maintained whenever possible, though temporary restrictions may occur during active construction. Your access route may need to change from day to day, including coming from the opposite direction.
- When driveways are impacted, crews will coordinate directly with residents. Please look for notices delivered to your door.
- Island View Circle will experience the most significant access limitations due to it being one way in/out.
- Crews will work to provide a temporary bypass access road whenever possible. However, limited public right-of-way and deep utility work may limit this possibility at times.
- If access is temporarily unavailable, residents will be asked to park on adjacent streets during work hours. This will be communicated in advance. Onsite project staff will be available to assist where possible.
- During major construction operations, residents are encouraged to schedule package delivery for pickup at a local carrier hub, if possible.
Mail, Trash & Recycling
- Temporary mailboxes will be installed to serve Island View Road, Island Circle, Island View Circle, and Fremont Avenue when needed.
- It is possible that USPS requires temporary mailboxes for more streets than are identified above.
- You will receive advance notice before mail service is relocated along with the location of the temporary mailbox bank. This will be coordinated directly with the USPS postmaster who will identify the temporary mailbox bank location.
- Your existing mailbox will be removed/salvaged, if possible, and then reinstalled at the conclusion of construction.
- Trash and recycling service will continue as normal.
- Please place bins as directed; crews will relocate them for pickup by the garbage haulers, if necessary.
Irrigation and Dog Fencing
- Irrigation systems and dog fences impacted by construction will be repaired.
- Please mark sprinkler heads and invisible dog fences in advance of construction on your street, if possible. This will help crews identify damage requiring repairs.
- Any damage will be documented and restored by the contractor during boulevard restorations. We encourage residents to notify the project team of damage to your facilities by sending an email to the project email address (below) to ensure it is included on our repairs tracking list.
Contact Us
For general questions, concerns, or to be directed to the right contact, please reach out to: [email protected] or (952) 373-0176.
The City of Prior Lake and their consultant, Bolton & Menk, will also have staff onsite during construction who can assist with questions and general access needs.
Stay Informed
Weekly construction updates will be emailed throughout the project, and additional or daily updates will be sent during major operations that impact access. Advanced notices will be provided for street closures, utility shutdowns, mailbox changes, concrete work, etc.
Thank you for your cooperation as we complete these important infrastructure improvements. We appreciate your patience as we work to improve the Northwood Road area.
Schedule
Survey Work, Preliminary Design, and Feasibility Study: Fall 2024 – Spring 2025
Design: 2025 – 2026
Construction: 2026 – 2027