Top

Street Improvement Project – West

Eagle Ridge Drive W Area, 7TH Avenue NW Area, & 21ST Avenue SW Area

Proposed Improvements

The City of Willmar is planning to improve the Eagle Ridge Drive W Area, 7TH Avenue NW Area, & 21ST Avenue SW Area.

Improvements include:

  • Asphalt surfacing
  • Concrete curb and gutter spot repair

construction newsletter has been distributed to all residents within the project area. This newsletter outlines the general sequence of construction and provides estimated timeframes for each phase. Moving forward, all project updates will be posted on the project website and distributed electronically to subscribers via email and text message.

If you have any questions or concerns that are not addressed in the newsletter or with this update, please do not hesitate to reach out to the project contacts listed on the website.

Construction Updates

July 7, 2025

Construction activities for the West Street Improvement Project have been delayed due to inclement weather, and the Contractor is now scheduled to begin operations in the Eagle Ridge Drive West (Phase 1) area starting July 18th, 2025.

The Contractor’s anticipated schedule for the three weeks following July 18, 2025 is as follows:

Phase 1 – Eagle Ridge Drive West Area (Full Depth Reclamation)

Friday July 18, 2025

  • Install traffic control devices
  • Install erosion control devices
  • Concrete/asphalt sawing in preparation for removals

Week of July 21, 2025

  • Reclaim operations to grind the pavement and underlying gravel base
  • Salvage reclaim material, excavate subgrade
  • Install salvage reclaim

Week of July 28, 2025

  • Salvage reclaim material, excavate subgrade (continued)
  • Install salvage reclaim (continued)

Week of August 4, 2025

  • Salvage reclaim material, excavate subgrade (complete)
  • Install salvage reclaim (complete)
  • Concrete removals
  • Storm sewer spot repair on Eagle Ridge Drive West
  • Concrete Spot Placement (7 day cure time)

Phase 2 – Fairway Drive (Mill & Overlay)

Friday July 18, 2025

  • Install traffic control devices
  • Install erosion control devices
  • Concrete/asphalt sawing in preparation for removals

Week of July 21, 2025

  • No work

Week of July 28, 2025

  • No work

Week of August 4, 2025

  • Asphalt milling operations
  • Concrete removals

Updates for Phases 3 through 6 will be provided as construction progresses.

We appreciate your patience and understanding as we work to improve your streets.

Contractor

Duininck Incorporated

Prinsburg, MN

Documents

Construction Newsletter 01 – Revised

Construction Newsletter 01

Sign Up for Project Updates

Engineer Contacts

Nate Thein
On-site Construction Representative, Bolton & Menk, Inc.
(320)-979-9070
Nate.Thein@bolton-menk.com

Spencer Johnson
Project Manager, Bolton & Menk, Inc.
(320)-979-6136
Spencer.Johnson@bolton-menk.com

Contractor Contact

Crystal Swanson
Project Manager, Duininck Inc.
(320)-212-9384
crystalswanson@duininck.com