Top

Street Improvement Project – West

Eagle Ridge Drive W Area, 7TH Avenue NW Area, & 21ST Avenue SW Area

Proposed Improvements

The City of Willmar is planning to improve the Eagle Ridge Drive W Area, 7TH Avenue NW Area, & 21ST Avenue SW Area.

Improvements include:

  • Asphalt surfacing
  • Concrete curb and gutter spot repair

construction newsletter has been distributed to all residents within the project area. This newsletter outlines the general sequence of construction and provides estimated timeframes for each phase. Moving forward, all project updates will be posted on the project website and distributed electronically to subscribers via email and text message.

If you have any questions or concerns that are not addressed in the newsletter or with this update, please do not hesitate to reach out to the project contacts listed on the website.

Construction Updates

September 26, 2025

The Contractor’s anticipated schedule for the next three weeks is provided below.  As always, this schedule is subject to change based on weather conditions.

Phase 1 – Eagle Ridge Drive West Area (Full Depth Reclamation)

  • Phase 1 is substantially completed. Moving forward the contractor will intermittently complete punch list items.  If there are any items that you believe need to be addressed prior to the completion of the project, please contact Nate Thein at the contact information provided.

Phase 2 – Fairway Drive NE (Mill & Overlay)

  • Phase 2 is substantially completed. Moving forward the contractor will intermittently complete punch list items.  If there are any items that you believe need to be addressed prior to the completion of the project, please contact Nate Thein at the contact information provided

Phase 3 – 29th Street NW (Full Depth Reclamation)

Week of September 29, 2025

  • Salvage reclaim material and excavate subgrade
  • Install salvaged reclaim material

Week of October 6, 2025

  • Complete installation of salvaged reclaim
  • Concrete removals
  • Concrete placement (7 day cure time)
  • Grading of the road section

Week of October 13, 2025

  • Tolerancing of gravel base in preparation for asphalt paving

Phase 4 – 7th Avenue NW (Full Depth Reclamation)

Week of September 29, 2025

  • Complete grading of the park trail and basketball court
  • Concrete removals

Week of October 6, 2025

  • Concrete placement (7 day cure time)
  • Grading road section

Week of October 13, 2025

  • Tolerancing of gravel base in preparation for asphalt paving

Phase 5 – 24th Street SW 20th & 21st Avenue SW (Full  Depth Reclamation)

Week of September 29, 2025

  • No work

Week of October 6, 2025

  • Reclaim road section (October 3)

Week of October 13, 2025

  • Salvage reclaim material and excavate subgrade
  • Install salvaged reclaim
  • Concrete removals

Phase 6 – 21st Avenue SW & 22nd Street SW (Mill & Overlay)

Week of September 29, 2025

  • No work

Week of October 6, 2025

  • No work

Week of October 13, 2025

  • Concrete removals

Additional Notes

Turf Establishment Care

To give your grass the best opportunity to flourish please consider the following:

  • Water 1 – 2 times a day for 10 – 15 minutes.
  • Do not rake the hydromulch up, it contains seed & fertilizer.  The hydromulch will naturally decompose.
  • Do not add any chemicals or fertilizers to the newly seeded area. We have already added fertilizer and pre-emergent weed killer. Adding more can potentially burn the new grass seed.
  • Avoid foot traffic on newly seeded areas.
  • All newly seeded areas for this project will be re-evaluated in the spring of 2026 for warranty work.

New Concrete Notice
Please avoid driving on newly poured concrete curbs and driveways for at least 7 days to allow proper curing and strength development.

7th Avenue NW Temporary Access

Since 7th Avenue NW provides the only access to County Road 5 from the 33rd Street NW development and Valleyside Townhomes, the City has provided a temporary access road through Valleyside Townhomes and the Regency Mobile Home Park properties. Prior to construction operations on 7th Avenue NW, detour signage will be installed to help drivers navigate to County Road 5 through the temporary access road. Please refer to the 7th Avenue NW Area phasing figure for a visual aid.

We appreciate your patience and understanding as we work to improve your streets.

Contractor

Duininck Incorporated

Prinsburg, MN

Documents

Construction Newsletter 01 – Revised

Construction Newsletter 01

Sign Up for Project Updates

Engineer Contacts

Nate Thein
On-site Construction Representative, Bolton & Menk, Inc.
(320)-979-9070
Nate.Thein@bolton-menk.com

Spencer Johnson
Project Manager, Bolton & Menk, Inc.
(320)-979-6136
Spencer.Johnson@bolton-menk.com

Contractor Contact

Crystal Swanson
Project Manager, Duininck Inc.
(320)-212-9384
crystalswanson@duininck.com