Project Updates – May, 2021
With good weather hopefully here to stay, crews will be on site to finish construction activities from last fall. Crews will be picking rocks from topsoil placed last fall, planting trees, seeding, and completing other tasks to finalize the construction efforts. Concrete crews will also be on site to replace some warranty items relating to cracked concrete.
A punch list has been created of items the contractor needs to complete prior to final acceptance of the project. If you are aware of any items that do not appear to be getting addressed, please reach out to Jon De Graaf at 712-363-5680 or email at jonathan.degraaf@bolton-menk.com.