May 9, 2025
There will be a temporary water shut off on Wednesday May 14th on Park Avenue from 11th Street W to 7th Street W. Please refer to the map on page 2 of the full newsletter for a more detailed area of what properties will be affected by this shut off.
Creamery Avenue N will remain closed from Harris Creek to CSAH 21 until further notice. Perry Avenue N and Main Street will be closed to through traffic and experience some temporary closures during construction.
The following work has been scheduled for May.
- Sanitary sewer, watermain and storm sewer construction on Perry Avenue N, Park Avenue N and 11th
- Storm Sewer and watermain on Main Street.
- Perry Avenue N road grading and reconstruction will begin mid month.
- Final grading and turf establishment on Creamery Avenue N to begin late May.
Contractor
R. L. Larson Excavating, Inc.
Sign up for project updates!
Contact Us
Kent Louwagie, P.E.
Browerville City Engineer
Cell: 320-905-5446
Email: kent.louwagie@bolton-menk.com
Jeremy Boots, P.E.
Project Manager
Cell: 320-895-0137
Email: jeremy.boots@bolton-menk.com
Brandon DeWolf
Construction Representative (RPR)
(onsite full-time)
Cell: 612-750-0353
Email: brandon.dewolf@bolton-menk.com