Project Updates
October 10, 2025
11th Steet West will be closed until the middle of November.
RL Larson is in the process of installing revised storm sewer, curb and gutter and an upgraded street section on 11th Street West.
- Rough grading and gravel installation on 11th Street West will continue until the middle of next week.
- Curb on 11th Street West is scheduled to be installed around October 15. Once the new concrete curb and driveway pavement is constructed, there will be a seven-day “cure” period. During this time, you will not be able to drive over the new curb or onto the new concrete.
- Pavement is scheduled to be installed around October 21.
- Final grading and turf establishment on 11th Street West will proceed the pavement installation.
- 11th Street West is scheduled to be reopened to the public by the end of November.
The final paving of all streets and punch list items will be addressed in 2026.
Contractor
R. L. Larson Excavating, Inc.
Sign up for project updates!
Contact Us
Kent Louwagie, P.E.
Browerville City Engineer
Cell: 320-905-5446
Email: kent.louwagie@bolton-menk.com
Jeremy Boots, P.E.
Project Manager
Cell: 320-895-0137
Email: jeremy.boots@bolton-menk.com
Wayne Duhoux
Construction Representative (RPR)
(onsite full-time)
Cell: (320) 204-9430
Email: Wayne.Duhoux@bolton-menk.com