November 11, 2025
11th Street West is open to local traffic but there may be some temporary closures during the turf establishment / punch list / minor utility adjustments process.
For the most part RL Larson has completed all the tasks that they will perform in 2025 except for minor work at the lift stations on Creamery Avenue and the main lift station on East Miltona Road.
Final paving of all streets in the project area, turf establishment issues, and punch list items will be addressed in 2026. Please be patient with the turf establishment, RL Larson has ensured us they will address legitimate concerns in the spring. Please contact us to document your concerns.
Contractor
R. L. Larson Excavating, Inc.
Sign up for project updates!
Contact Us
Kent Louwagie, P.E.
Browerville City Engineer
Cell: 320-905-5446
Email: kent.louwagie@bolton-menk.com
Jeremy Boots, P.E.
Project Manager
Cell: 320-895-0137
Email: jeremy.boots@bolton-menk.com
Wayne Duhoux
Construction Representative (RPR)
(onsite full-time)
Cell: (320) 204-9430
Email: Wayne.Duhoux@bolton-menk.com