2025 Street & Utility Improvements

Top
 

Updates

Neighborhood Information

Irish Court

Click to view the Irish Court Construction Flyer

Click to view the Irish Court Paving Notice

Week of September 15 – Miscellaneous cleanup

Week of September 22 No work currently scheduled

Teal Pass Estates

Click to view the Teal Pass Estates Construction Flyer.

Week of September 15 – Miscellaneous cleanup

Week of September 22 No work currently scheduled

55th/57th/Julep and 55th St N (Lake Elmo Vista)

Click to view the 55th/57th/Julep and 55th St N (Lake Elmo Vista) Construction Flyer

Week of September 15 – Concrete curb (Monday, September 15 and Tuesday, September16). Concrete driveways and finish curb (Tuesday, September 16). Backfilling behind curb with topsoil (Wednesday, September 17 – Friday, September 19). Grading and tolerancing road (Thursday, September 18 – Friday, September 19).

Week of September 22 Paving base (tentatively Wednesday, September 24, weather permitting). A flyer will be sent out providing more information regarding base lift paving.

 59th Street Circle N (Prairie Hamlet)

Click to view the Prairie Hamlet Construction Flyer.

Week of September 15 – Miscellaneous cleanup

Week of September 22 No work currently scheduled

Weekly Updates

Project updates will be posted when new information becomes available.

Week of September 15

59th Street Court N (Prairie Hamlet): The contractor does not currently have any major work scheduled for this week. They may be on site taking care of miscellaneous project related tasks. Notification for the final layer of paving will be sent out once a definitive date is established.

Irish Ct: The contractor does not currently have any major work scheduled for this week. They may be on site taking care of miscellaneous project related tasks. Notification for the final layer of paving will be sent out once a definitive date is established.

Teal Pass Estates: The contractor does not currently have any major work scheduled for this week. They may be on site taking care of miscellaneous project related tasks. Notification for the final layer of paving will be sent out once a definitive date is established.

55th/57th/Julep and 55th St N (Lake Elmo Vista): The contractor will be grading the road and backfilling topsoil behind newly installed curb.

Past Meetings

Click the name of the meeting you are interested in to view the presentation.

June 11, 2025: Neighborhood Construction Open House

April 24, 2025

April 23, 2025

April 17, 2025

January 28-29, 2025: Initial Neighborhood Meetings

Click below to sign up for project updates!


Sign up for project updates

To sign up for project updates, please enter your contact information below.

Contact Us!


Alec Rynda

Project Engineer

(612) 468-9572

 

Mike Rusenovich

Project Engineer

(612) 546-0751

Mike.Rusenovich@bolton-menk.com