2025 Street & Utility Improvements

Top
 

Updates

Neighborhood Information

Irish Court

Click to view the Irish Court Construction Flyer

Click to view the Irish Court Paving Notice

The contractor has not provided a definitive date when they will have availability to finish the remainder of the paving. A tentative date of Tuesday, October 28 has been communicated. If availability opens up before then, the contractor will show up on short notice to complete the work.

Teal Pass Estates

Click to view the Teal Pass Estates Construction Flyer.

Major work for the project has been completed. The contractor may be on site taking care of miscellaneous tasks and completing final restoration in the coming weeks.

55th/57th/Julep and 55th St N (Lake Elmo Vista)

Click to view the 55th/57th/Julep and 55th St N (Lake Elmo Vista) Construction Flyer

The contractor has not provided a definitive date when they will be available to finish the final layer of asphalt on 55th St N off Keats Avenue. A tentative date of Tuesday, October 28 has been communicated. If availability opens up before then, the contractor will show up on short notice to complete the work. In the meantime, the contractor may be on site taking care of miscellaneous tasks. Private utility work is scheduled for this week as well as potential storm sewer work.

 59th Street Circle N (Prairie Hamlet)

Click to view the Prairie Hamlet Construction Flyer.

The contractor has not provided a definitive date when they will be available to finish the final layer of asphalt. A tentative date of Tuesday, October 28 has been communicated. If availability opens up before then, the contractor will show up on short notice to complete the work. In the meantime, the contractor may be on site taking care of miscellaneous tasks.

Weekly Updates

Project updates will be posted when new information becomes available.

Week of October 13

59th Street Court N (Prairie Hamlet): The contractor has not provided a definitive date when they will be available to pave the final layer of asphalt. A tentative date of Tuesday, October 28 has been communicated. If availability opens up before then, the contractor will show up on short notice to complete the work. In the meantime, the contractor may be on site taking care of miscellaneous tasks.

Irish Ct: The contractor has not provided a definitive date when they will be finish the remainder of the paving. A tentative date of Tuesday, October 28 has been communicated. If availability opens up before then, the contractor will show up on short notice to complete the work.

Teal Pass Estates: Major work for the project has been completed. The contractor may be on site taking care of miscellaneous tasks and completing final restoration in the coming weeks.

55th/57th/Julep and 55th St N (Lake Elmo Vista): The contractor has not provided a definitive date when they will be available to finish the final layer of asphalt on 55th St N off Keats Avenue. A tentative date of Tuesday, October 28 has been communicated. If availability opens up before then, the contractor will show up on short notice to complete the work. In the meantime, the contractor may be on site taking care of miscellaneous tasks. Private utility work is scheduled for this week as well as potential storm sewer work.

To accommodate contractor availability and maintain alignment with their schedules, the project schedule may change with short notice for certain work to be completed. The city plans to provide as much notice as possible, given what information is provided by the contractor. However, the final lift of paving may be scheduled with less than a week’s notice due to timing constraints. As a general practice, please refrain from parking on the street during construction hours of 7 a.m. to 7 p.m. Click to see information regarding paving.

Past Meetings

Click the name of the meeting you are interested in to view the presentation.

June 11, 2025: Neighborhood Construction Open House

April 24, 2025

April 23, 2025

April 17, 2025

January 28-29, 2025: Initial Neighborhood Meetings

Click below to sign up for project updates!


Sign up for project updates

To sign up for project updates, please enter your contact information below.

Contact Us!


Alec Rynda

Project Engineer

(612) 468-9572

 

Mike Rusenovich

Project Engineer

(612) 546-0751

Mike.Rusenovich@bolton-menk.com