Neighborhood Information
Irish Court
Click to view the Irish Court Construction Flyer
Click to view the Irish Court Paving Notice
Week of July 21 – Preparation for wear course lift (No date scheduled yet).
Teal Pass Estates
Click to view the Teal Pass Estates Construction Flyer.
Week of July 21 – Curb install is being delayed due to weather and contractor availability. We will provide an update when we know the date for curb installation.
Week of July 28 – If curb has been placed, Backfilling behind the curb and tolerancing for the first layer of paving.
55th/57th/Julep and 55th St N (Lake Elmo Vista)
The 55th/57th/Julep and 55th St N (Lake Elmo Vista) Construction Flyer will be added before construction begins.
55th/57th/Julep and 55th St N (Lake Elmo Vista) construction has been delayed – construction will likely begin in August depending on the contractor’s progress in other neighborhoods.
59th Street Circle N (Prairie Hamlet)
Click to view the Prairie Hamlet Construction Flyer.
July 15, 2025 – Prairie Hamlet construction work is scheduled to begin.
Week of July 21 – Storm sewer Monday, July 21 through Wednesday July 23. Drain tile install Thursday, July 24.
Week of July 28 – Tolerancing for curb
Weekly Updates
Project updates will be posted when new information becomes available.
Week of July 21, 2025
59th Street Circle N (Prairie Hamlet): The contractor will be installing storm sewer Monday, July 21 through Wednesday July 23, and installing drain tile the days following.
Irish Ct: The contractor is preparing for the second and final layer of paving. No date is set yet, we will provide an update when we know the date for pavement installation.
Teal Pass Estates: Curb install is being delayed due to weather and contractor availability. There is no scheduled date yet, and we will provide an update when we know the date for curb installation.
55th/57th/Julep and 55th St N (Lake Elmo Vista): Construction has been delayed. At this time, construction is expected to begin in August after 59th Street Circle work. The schedule for this neighborhood is still rough – schedule updates will be posted on the project website when they are available.
Past Meetings
Click the name of the meeting you are interested in to view the presentation.
June 11, 2025: Neighborhood Construction Open House
April 24, 2025
April 23, 2025
April 17, 2025
January 28-29, 2025: Initial Neighborhood Meetings
Click below to sign up for project updates!
Contact Us!
Shane Olson
Construction Inspector
612.997.2676
Mike Rusenovich
Project Engineer
612.546.0751