Neighborhood Information
Irish Court
Click to view the Irish Court Construction Flyer
Monday, July 7 – First layer of paving is scheduled to begin. Click to view the paving notice for more information.
Week of June 30 – Removing excess material, tolerancing for paving.
Week of July 7 – Paving base lift on Monday, July 7. Utility adjustments.
Teal Pass Estates
Click to view the Teal Pass Estates Construction Flyer.
Week of June 30 – Mailboxes removed on Thursday, July 3. Installing drain tile.
Week of July 7 – Storm sewer.
55th/57th/Julep and 55th St N (Lake Elmo Vista)
The 55th/57th/Julep and 55th St N (Lake Elmo Vista) Construction Flyer will be added before construction begins.
55th/57th/Julep and 55th St N (Lake Elmo Vista) construction has been delayed – construction will likely begin in August depending on the contractor’s progress in other neighborhoods.
59th Street Circle N (Prairie Hamlet)
Click to view the Prairie Hamlet Construction Flyer.
July 15, 2025 – Prairie Hamlet construction work is scheduled to begin.
Week of July 14 – Reclaiming road
Weekly Updates
Project updates will be posted when new information becomes available.
Week of June 30, 2025
59th Street Circle N (Prairie Hamlet) – The contractor has adjusted their schedule and plans to begin construction in Prairie Hamlet earlier than expected. At this time, construction is scheduled to begin on July 15, 2025 (weather dependent).
Irish Ct: The contractor is preparing for the first layer of paving (scheduled for 7/8). A paving notice has been delivered to the neighborhood and is also available on this website.
Teal Pass Estates: The contractor will be removing mailboxes on Thursday, July 3 and placing temporary mailboxes, as well as installing drain tile this week.
55th/57th/Julep and 55th St N (Lake Elmo Vista) construction has been delayed. At this time, construction is expected to begin in August after 59th Street Circle work. The schedule for this neighborhood is still rough – schedule updates will be posted as they are available.
June 25, 2025 – Irish Court Schedule Update
Concrete work has been delayed until Thursday, June 26, due to weather. Irish Court residents should park outside of the neighborhood beginning at 7 a.m. on Thursday, June 26. We apologize for the inconvenience and appreciate your patience as construction continues.
Week of June 23, 2025
Irish Ct concrete curb work is scheduled to begin on Wednesday, June 25 and driveways poured on Thursday, June 26 (weather dependent). Concrete work will affect driveway access for approximately seven days.
Construction in Teal Pass Estates will begin the week of June 23. Reclaim and removals will start Tuesday, June 24.
Past Meetings
Click the name of the meeting you are interested in to view the presentation.
June 11, 2025: Neighborhood Construction Open House
April 24, 2025
April 23, 2025
April 17, 2025
January 28-29, 2025: Initial Neighborhood Meetings
Click below to sign up for project updates!
Contact Us!
Shane Olson
Construction Inspector
612.997.2676
Mike Rusenovich
Project Engineer
612.546.0751