2025 Street & Utility Improvements

Top
 

Updates

Neighborhood Information

Irish Court

Click to view the Irish Court Construction Flyer

Click to view the Irish Court Paving Notice

Week of July 21 – Preparation for wear course lift (No date scheduled yet).

Teal Pass Estates

Click to view the Teal Pass Estates Construction Flyer.

Week of July 21 – Curb install is being delayed due to weather and contractor availability. We will provide an update when we know the date for curb installation.

Week of July 28 – If curb has been placed, Backfilling behind the curb and tolerancing for the first layer of paving.

55th/57th/Julep and 55th St N (Lake Elmo Vista)

The 55th/57th/Julep and 55th St N (Lake Elmo Vista) Construction Flyer will be added before construction begins.

55th/57th/Julep and 55th St N (Lake Elmo Vista) construction has been delayed – construction will likely begin in August depending on the contractor’s progress in other neighborhoods.

 59th Street Circle N (Prairie Hamlet)

Click to view the Prairie Hamlet Construction Flyer.

July 15, 2025 – Prairie Hamlet construction work is scheduled to begin.

Week of July 21 – Storm sewer Monday, July 21 through Wednesday July 23. Drain tile install Thursday, July 24.

Week of July 28 – Tolerancing for curb

Weekly Updates

Project updates will be posted when new information becomes available.

Week of July 21, 2025

59th Street Circle N (Prairie Hamlet): The contractor will be installing storm sewer Monday, July 21 through Wednesday July 23, and installing drain tile the days following.

Irish Ct: The contractor is preparing for the second and final layer of paving. No date is set yet, we will provide an update when we know the date for pavement installation.

Teal Pass Estates: Curb install is being delayed due to weather and contractor availability. There is no scheduled date yet, and we will provide an update when we know the date for curb installation.

55th/57th/Julep and 55th St N (Lake Elmo Vista): Construction has been delayed. At this time, construction is expected to begin in August after 59th Street Circle work. The schedule for this neighborhood is still rough – schedule updates will be posted on the project website when they are available.

Past Meetings

Click the name of the meeting you are interested in to view the presentation.

June 11, 2025: Neighborhood Construction Open House

April 24, 2025

April 23, 2025

April 17, 2025

January 28-29, 2025: Initial Neighborhood Meetings

Click below to sign up for project updates!


Sign up for project updates

To sign up for project updates, please enter your contact information below.

Contact Us!


Shane Olson

Construction Inspector

612.997.2676

 

Mike Rusenovich

Project Engineer

612.546.0751

Mike.Rusenovich@bolton-menk.com