Neighborhood Information
Irish Court
Click to view the Irish Court Construction Flyer
Click to view the Irish Court Paving Notice
Week of September 15 – Miscellaneous cleanup
Week of September 22 – No work currently scheduled
Teal Pass Estates
Click to view the Teal Pass Estates Construction Flyer.
Week of September 15 – Miscellaneous cleanup
Week of September 22 – No work currently scheduled
55th/57th/Julep and 55th St N (Lake Elmo Vista)
Click to view the 55th/57th/Julep and 55th St N (Lake Elmo Vista) Construction Flyer
Week of September 15 – Concrete curb (Monday, September 15 and Tuesday, September16). Concrete driveways and finish curb (Tuesday, September 16). Backfilling behind curb with topsoil (Wednesday, September 17 – Friday, September 19). Grading and tolerancing road (Thursday, September 18 – Friday, September 19).
Week of September 22 – Paving base (tentatively Wednesday, September 24, weather permitting). A flyer will be sent out providing more information regarding base lift paving.
59th Street Circle N (Prairie Hamlet)
Click to view the Prairie Hamlet Construction Flyer.
Week of September 15 – Miscellaneous cleanup
Week of September 22 – No work currently scheduled
Weekly Updates
Project updates will be posted when new information becomes available.
Week of September 15
59th Street Court N (Prairie Hamlet): The contractor does not currently have any major work scheduled for this week. They may be on site taking care of miscellaneous project related tasks. Notification for the final layer of paving will be sent out once a definitive date is established.
Irish Ct: The contractor does not currently have any major work scheduled for this week. They may be on site taking care of miscellaneous project related tasks. Notification for the final layer of paving will be sent out once a definitive date is established.
Teal Pass Estates: The contractor does not currently have any major work scheduled for this week. They may be on site taking care of miscellaneous project related tasks. Notification for the final layer of paving will be sent out once a definitive date is established.
55th/57th/Julep and 55th St N (Lake Elmo Vista): The contractor will be grading the road and backfilling topsoil behind newly installed curb.
Past Meetings
Click the name of the meeting you are interested in to view the presentation.
June 11, 2025: Neighborhood Construction Open House
April 24, 2025
April 23, 2025
April 17, 2025
January 28-29, 2025: Initial Neighborhood Meetings
Click below to sign up for project updates!
Contact Us!
Alec Rynda
Project Engineer
(612) 468-9572
Mike Rusenovich
Project Engineer
(612) 546-0751