Upcoming Meetings
An in-person neighborhood construction open house will be held on Wednesday, June 11, 2025 at Lake Elmo City Hall. After a short (15 minute) presentation reviewing construction impacts and schedules, residents may meet with the project team and discuss project questions.
What: Lake Elmo 2025 Street and Utility Improvements Neighborhood Construction Open House
Where: Lake Elmo City Hall (3880 Laverne Ave N, Lake Elmo, MN 55042)
When: Wednesday, June 11 @ 5:30 p.m. – 6:30 p.m.
Past Meetings
Click the name of the meeting you are interested in to view the presentation.
April 24, 2025
April 23, 2025
April 17, 2025
January 28-29, 2025: Initial Neighborhood Meetings
Newsletters
Newsletters will be added as they become available.
Weekly Updates
Project updates will be posted when new information becomes available.
Week of 5/26/2025
The project contractor, Valley Paving, intends to begin work in late June. Their preliminary schedule is as follows:
- Late June: Begin Irish Court N
- Mid-July: Begin Teal Pass Estates
- Early August: Begin 55th/57th/Julep and 55th Street N (Lake Elmo Vista)
- Mid-August: Begin Prairie Hamlet
Please note this is a tentative schedule – depending on the needs of the project, these dates may change or be updated. Stay informed with project updates if you have concerns about the schedule.
Residents are responsible for removing private property (sprinkler systems, electric dog fences, landscaping etc.) from the City right-of-way before construction. A practical effort will be made to coordinate removals, but repair and replacement of private property will be the property owner’s responsibility should any damage occur.
A resident update letter was sent by the City with information on the upcoming open house and impacts to private property. Click to view the resident update letter.
Week of 5/5/2025
- A public hearing for the project was held at the May 6th, 2025 Council Meeting. Following the hearing, the City Council ordered the improvements and awarded a construction contract to Valley Paving, Inc.
- At this time, Valley Paving expects to begin construction around late June. This is a rough early estimate – the schedule may change quickly depending on the contractor’s availability. Once the project is awarded, the contractor may begin work at any time – please stay aware of construction updates.
- Once a firmer construction start date is known, the City will hold a neighborhood construction meeting to provide project information and review construction impacts. The City will send a resident letter with meeting and construction information as well as updating this website.
Click below to sign up for project updates!
Contact Us!
Nathan Stanley
City Engineer
763.358.1997
Nathan.Stanley@bolton-menk.com
Chad Isakson
Asst. City Engineer
651.728.3073
Mike Rusenovich
Project Engineer
612.546.0751