County Highway 21 Downtown Prior Lake Reconstruction

Top
Sign Up for Project Updates!
Please enter your preferred contact information below.

Project Hotline & Email

612-357-7270
movingforward13-21@bolton-menk.com

13-21 Construction Overview

Highway 13 Construction Overview

What is being built?

  • Check out this video to see what is being built on County Highway 21 and the 13-21 intersection. 
  • Check the Duluth Ave website to view improvements to Duluth Ave.
  • Highway 13 work includes resurfacing and drainage improvements. Check out MnDOT’s project website for more info.

Project completion timeline

Crews have made good project progress over the last several weeks, with a majority of both Highway 13 and Highway 21 being paved. Over the next few weeks, crews will continue to finish major curb, paving, and restoration work. Highway 13 work is anticipated to be complete by mid-November, and work on County Highway 21 is scheduled to last until Thanksgiving. Thank you for your patience as crews continue improving these roadways!

Downtown Construction Progress 0

Downtown Update

October 17, 2019

Staging information

Stage 2: County Highway 21 from West Ave to Main Ave and Highway 13 from County Highway 21 to Franklin Trail

Progress and Upcoming Work

This week:

  • 21 was paved from Duluth to Main!
  • Geofoam block installation finished on the south leg of the 13-21 intersection
  • Crews graded the roadway and areas behind curb

Next week:

  • Curb installation will occur at Main
  • Crews will finish backfilling and grading the south leg of the 13-21 intersection and install curb
  • Crews will pave the asphalt trail on the south side of 21

Highway 13 Construction Progress 0

Highway 13 Update

October 17, 2019

Staging information

  • Stage 1 complete!
  • Stage 2 complete!
  • Stage 4: Highway 13 from County Road 12 to Franklin Trail
  • Stage 3: Highway 13 from Fairlawn Ave to County Road 12

Progress and Upcoming Work

This week:

Stage 3

  • Crews finished storm sewer and culvert installation
  • Crews poured curb on south side of the median between 170th and Panama

Stage 4

  • Paving occurred from Franklin Trail to Panama Ave!
  • Crews installed the pipe crossing at Panama Ave
  • Crews work on grading the trail on the north side of 13 near Duluth
  • Curb and pedestrian ramps were poured

Next week:

Stage 3

  • Crews will begin grading the acceleration lane and ditches
  • Crews will grade the road in preparation for paving, which will happen late next week or early the following week!

Stage 4

  • Crews will pave the trail on the north side of Highway 13 near Duluth
  • Guardrail installation will occur
  • Crews will continue miscellaneous pedestrian ramp work

13-21 Roundabout 0

13-21 Roundabout Update

The 13-21 roundabout will be built from the spring-July of 2020.