Top

WEEKLY UPDATE

October 25, 2022

Red Wing Riverview Skyway is open!

Old West Main Street Update:

The contractor continues to make good progress week to week. All the concrete work is expected to be completed on Jackson Street and the alley this week. No other concrete work is planned until next spring to complete any warranty and/or minor repair work. The paving of the final lift of bituminous between Buchanan and Jefferson St is scheduled for this week Friday. The remaining bituminous paving in the alley and miscellaneous driveway tie-ins is anticipated late next week to allow sufficient cure time for the new concrete placed within the alley. The striping of the parking stalls between Jefferson and TH 61 (Main St) was successfully completed last week and all permanent signing is scheduled to be installed this coming Monday. The energizing of the lights west of Jefferson is still anticipated in the next couple of weeks. All the conduit is in place, the contractor just needs to finish pulling the wire and then hook everything up. The remaining wood benches, wooden light poles, kiosk, and entry monuments at the intersection of TH 61/ Main St are still in production and anticipated to be installed later this fall.

Also, starting next week the contractor’s subconsultant Terracon out of Rochester, MN will be completing the post construction building condition survey. This survey is planned to include all items inspected during the preconstruction survey to document any observed changes.

PAST UPDATES

The most recent project update was sent out on Tuesday, October 25th. Si te gustaría recibir estas últimas noticias de la semana en español, por favor envié un correo electrónico a Michelle Leise a michelle.leise@ci.red-wing.mn.us.

Newsletter 1_2021-2-12 English           Newsletter 1_2021-2-12 Spanish

Newsletter 2_2021-2-26 English          Newsletter 2_2021-2-26 Spanish

Newsletter 3_2021-3-12 English           Newsletter 3_2021-3-12 Spanish

Newsletter 4_2021-3-26 English          Newsletter 4_2021-3-26 Spanish

Newsletter 5_2021-4-9 English            Newsletter 5_2021-4-9 Spanish

Newsletter 6_2021-4-23 English          Newsletter 6_2021-4-23 Spanish

Newsletter 7_2021-5-7 English            Newsletter 7_2021-5-7 Spanish

Newsletter 8_2021-5-21 English          Newsletter 8_2021-5-21 Spanish

Newsletter 9_2021-6-4 English            Newsletter 9_2021-6-4 Spanish

Newsletter 10_2021-6-18 English        Newsletter 10_2021-6-18 Spanish

Newsletter 11_2021-7-2 English           Newsletter 11_2021-7-2 Spanish

Newsletter 12_2021-7-16

Newsletter 13_2021-7-23

Newsletter 14_2021-7-30

Newsletter 15_2021-8-6

Newsletter 16_2021-8-13

Newsletter 17_2021-8-20

Newsletter 18_2021-8-27

Newsletter 19_2021-9-3

Newsletter 20_2021-9-10

Newsletter 21_2021-9-20

Newsletter 22_2021-9-24

Newsletter 23_2021-10-1

Newsletter 24_2021-10-8

Newsletter 25_2021-10-15

Newsletter 26_2021-10-22

Newsletter 27_2021-11-5

Newsletter 28_2021-11-12

Newsletter 29_2021-11-19

Newsletter 30_2022-3-25

Newsletter 31_2022-4-1

Newsletter 32_2022-4-8

Newsletter 33_2022-4-15

Newsletter 34_2022-4-22

Newsletter 35_2022-4-29

Newsletter 36_2022-5-6

Newsletter 37_2022-5-13

Newsletter 38_2022-5-20

Newsletter 39_2022-5-27

Newsletter 40_2022-6-3

Newsletter 41_2022-6-10

Newsletter 42_2022-6-17

Newsletter 43_2022-6-24

Newsletter 44_2022-7-1          Hwy 61 Open House Flyer

Newsletter 45_2022-7-11

Newsletter 46_2022-7-15

Newsletter 47_2022-7-22

Newsletter 48_2022-8-2

Newsletter 49_2022-8-12

Newsletter 50_2022-8-19

Newsletter 51_2022-9-2

Newsletter 52_2022-9-16

Newsletter 53_2022-9-23

Newsletter 54_2022-9-30

Newsletter 55_2022-10-7

Newsletter 56_2022-10-19

Newsletter 57_2022-10-25

Project Updates
To sign up for updates, please enter your contact information below.

Project Contacts:

Cory Bienfang, P.E. | Project Manager
507.995.2936
cory.bienfang@bolton-menk.com

Ryan Illa | City Project Manager
651.260.5956
ryan.illa@ci.red-wing.mn.us

Jay Owens, P.E. | City Engineer/ Engineering Director
651.385.3625
jay.owens@ci.red-wing.mn.us