Project Updates – Sept. 5, 2025

Completed work
- Poured sidewalk concrete on Olive Street and 2nd Street in Stage 3.
- Began excavating and placing gravel in the alley between Olive Street and Elm Street.
- Continued preparation work to remove all utility lines from the poles on Olive Street. Once all lines have been cleared, the poles will be taken down.
- Properties affected by this work will receive detailed notifications in advance. During the workday, best efforts will be made to accommodate regular access as much as possible.
Upcoming work
- Finish excavating and placing gravel in the alley between Olive Street and Elm Street and begin gutter installation.
- Finish paving driveways in Stage 3
- Begin restoration work (placing topsoil and sod) throughout the project area.
- Property owners will receive care instructions for the new sod when installed.
Contact us
Please contact our on-site project representative, Dalmas Omwoyo at
651-728-0312, with any questions, property specific needs or accommodations.
Previous Updates
Aug. 29, 2025
Completed work
- Paved:
- Olive Street from 1st Street to 2nd Street
- 2nd Street from Elm Street to the dead end
- Installed storm sewer from the alley between Olive Street and Elm Street and into Elm Street for future project connections.
- Continued preparation work to remove all utility lines from the poles on Olive Street. Once all lines have been cleared, the poles will be taken down.
- Properties affected by this work will receive detailed notifications in advance. During the workday, best efforts will be made to accommodate regular access as much as possible.
Upcoming work
- Pouring sidewalk concrete on Olive Street and 2nd Street in Stage 3.
- Excavate and place gravel in the alley between Olive Street and Elm Street.
Aug. 22, 2025
Completed work
- Poured Stage 3 concrete curb on Olive Street & 2nd Street.
- Began preparation work for Stage 3 sidewalks.
Upcoming work
- Begin installing storm sewer on Monday, Aug. 25 from the alley between Olive Street and Elm Street and into Elm Street for future project connections.
- Elm Street will be closed to through traffic and will be reopened by the end of the day.
- Continue preparing for Stage 3 sidewalk work.
- Prepare the Stage 3 gravel road base and begin initial paving work on Olive Street from 1st Street to 2nd Street and 2nd Street from Elm Street to the dead end.
- During this work the following areas will be closed:
- Olive Street from 1st Street to 2nd Street
- 2nd Street from Elm Street to the dead end
- 1st Street / Olive Street intersection
- The 1st Street / Olive Street intersection will reopen after work is completed.
- During this work the following areas will be closed:
Phase 4 Update – Aug. 20, 2025
The City Council accepted the feasibility study and called the improvement hearing for the Phase 4 project (shown in pink in the above map). This improvement hearing will be held on Monday, Sept. 15, at City Hall. Property owners impacted by this project will also receive a notice in the mail for this upcoming meeting. The tentative schedule for this final phase of reconstruction in the downtown area is:
- Final design: winter 2025/26
- Select a contractor: spring 2026
- Construction: summer through fall 2026
Aug. 15, 2025
Completed work
- Continued Stage 3 storm water installation on Olive Street and and in the alley between Olive Street and Elm Street.
- Continued Stage 3 road excavation on 2nd Street and Olive Street.
- Installed drain tile, irrigation and electrical conduits on 2nd Street and Olive Street.
- Completed Stage 3 light pole and banner pole base work.
- Continued to remove all overhead power lines in order to remove the poles.
Upcoming work
- Pour Stage 3 concrete curb on 2nd Street and Olive Street.
- Adjacent property owners will be notified of when concrete will be placed in front of their business.
- After the concrete curb is complete the contractor will begin preparing for sidewalk construction throughout Stage 3.
- Remove overhead power lines and poles.
- Affected properties will be notified with specifics.
- During the workday, best efforts will be made to accommodate regular access as much as possible.
Aug. 8, 2025
Completed work
- Continued Stage 3 utility work (water main, sanitary sewer installation) on Olive Street and 2nd Street.
- Began road excavation on 2nd Street west of Olive Street in Stage 3.
- Began Stage 3 light pole base construction.
- Took overhead power lines offline and prepared to remove the utility poles and lines. Once all lines are cleared, the poles will be taken down.
Upcoming work
- Continue Stage 3 light pole and banner pole base work.
- Continue road excavation on 2nd Street west of Olive Street.
- Install drain tile, irrigation and electrical conduits on 2nd Street west of Olive Street in Stage 3.
- Begin storm sewer installation in the alley between Olive Street and Elm Street.
- Remove overhead power poles.
- Affected properties will be notified with specifics.
- During the workday, best efforts will be made to accommodate regular access as much as possible.
August 1, 2025
Completed work
- Continued Stage 3 utility work (water main, sanitary sewer and storm sewer installation) on Olive Street.
- Continued Stage 2 restoration work.
- Continued preparation work for burying overhead utilities on Olive Street with placement of the transformer and removal of overhead utilities.
Upcoming work
- Continue Stage 3 utility work (sanitary sewer and water main) on 2nd Street between Olive Street and Elm Street.
- During utility connection work, water shutoffs may be needed to connect properties to the existing water system. Affected properties will be notified prior to shutoffs.
- Continue preparation work for burying overhead utilities on Olive Street with placement of the transformer and removal of overhead utilities.
- Affected properties will be notified with specifics.
- During the workday, best efforts will be made to accommodate regular access as much as possible.
July 25, 2025
Completed work
- Continued Stage 3 utility work on 2nd Street west of Olive Street.
- Continued Stage 1 and 2 restoration work.
- CenterPoint completed relocating gas main in the alley between Olive Street and Elm Street.
- Continued preparation work for burying overhead utilities on Olive Street with placement of the transformer and removal of overhead utilities.
Upcoming work
- Continue Stage 3 utility work on Olive Street and 2nd Street.
- During utility connection work, water shutoffs may be needed to connect properties to the existing water system. Affected properties will be notified prior to shutoffs.
PROJECT EMAIL/TEXT UPDATES
CONTACT
JON HAUKAAS, DIRECTOR OF PUBLIC SERVICES
City of Waconia
952-442-4265
COLTON LEE, PROJECT MANAGER
Bolton & Menk, Inc.
612-346-6059
JAKE SAULSBURY, P.E., CITY ENGINEER
Bolton & Menk, Inc.
jake.saulsbury@bolton-menk.com
612-756-4319
PROJECT DOCUMENTS
September 2022 Downtown Reconstruction, Phase 1 Project Feasibility Study
August 2023 Downtown Reconstruction, Phase 2 Project Feasibility Study
December 2024 Downtown Reconstruction, Phase 3 Project Feasibility Study
August 2025 Downtown Reconstruction, Phase 4 Project Feasibility Study