City of Waconia Downtown Reconstruction Project
Top
 

Project Updates

Project Updates – Sept. 5, 2025

Completed work

  • Poured sidewalk concrete on Olive Street and 2nd Street in Stage 3.
  • Began excavating and placing gravel in the alley between Olive Street and Elm Street.
  • Continued preparation work to remove all utility lines from the poles on Olive Street. Once all lines have been cleared, the poles will be taken down.
    • Properties affected by this work will receive detailed notifications in advance. During the workday, best efforts will be made to accommodate regular access as much as possible.

Upcoming work

  • Finish excavating and placing gravel in the alley between Olive Street and Elm Street and begin gutter installation.
  • Finish paving driveways in Stage 3
  • Begin restoration work (placing topsoil and sod) throughout the project area.
    • Property owners will receive care instructions for the new sod when installed.

Contact us

Please contact our on-site project representative, Dalmas Omwoyo at
651-728-0312, with any questions, property specific needs or accommodations.

Previous Updates

Aug. 29, 2025

Completed work

  • Paved:
    • Olive Street from 1st Street to 2nd Street
    • 2nd Street from Elm Street to the dead end
  • Installed storm sewer from the alley between Olive Street and Elm Street and into Elm Street for future project connections.
  • Continued preparation work to remove all utility lines from the poles on Olive Street. Once all lines have been cleared, the poles will be taken down.
    • Properties affected by this work will receive detailed notifications in advance. During the workday, best efforts will be made to accommodate regular access as much as possible.

Upcoming work

  • Pouring sidewalk concrete on Olive Street and 2nd Street in Stage 3.
  • Excavate and place gravel in the alley between Olive Street and Elm Street.

Aug. 22, 2025

Completed work

  • Poured Stage 3 concrete curb on Olive Street & 2nd Street.
  • Began preparation work for Stage 3 sidewalks.

Upcoming work

  • Begin installing storm sewer on Monday, Aug. 25 from the alley between Olive Street and Elm Street and into Elm Street for future project connections.
    • Elm Street will be closed to through traffic and will be reopened by the end of the day.
  • Continue preparing for Stage 3 sidewalk work.
  • Prepare the Stage 3 gravel road base and begin initial paving work on Olive Street from 1st Street to 2nd Street and 2nd Street from Elm Street to the dead end.
    • During this work the following areas will be closed:
      • Olive Street from 1st Street to 2nd Street
      • 2nd Street from Elm Street to the dead end
      • 1st Street / Olive Street intersection
    • The 1st Street / Olive Street intersection will reopen after work is completed.

Phase 4 Update – Aug. 20, 2025

The City Council accepted the feasibility study and called the improvement hearing for the Phase 4 project (shown in pink in the above map). This improvement hearing will be held on Monday, Sept. 15, at City Hall. Property owners impacted by this project will also receive a notice in the mail for this upcoming meeting. The tentative schedule for this final phase of reconstruction in the downtown area is:

  • Final design: winter 2025/26
  • Select a contractor: spring 2026
  • Construction: summer through fall 2026

Aug. 15, 2025

Completed work

  • Continued Stage 3 storm water installation on Olive Street and and in the alley between Olive Street and Elm Street.
  • Continued Stage 3 road excavation on 2nd Street and Olive Street.
  • Installed drain tile, irrigation and electrical conduits on 2nd Street and Olive Street.
  • Completed Stage 3 light pole and banner pole base work.
  • Continued to remove all overhead power lines in order to remove the poles.

Upcoming work

  • Pour Stage 3 concrete curb on 2nd Street and Olive Street.
    • Adjacent property owners will be notified of when concrete will be placed in front of their business.
    • After the concrete curb is complete the contractor will begin preparing for sidewalk construction throughout Stage 3.
  • Remove overhead power lines and poles.
    • Affected properties will be notified with specifics.
    • During the workday, best efforts will be made to accommodate regular access as much as possible.

Aug. 8, 2025

Completed work

  • Continued Stage 3 utility work (water main, sanitary sewer installation) on Olive Street and 2nd Street.
  • Began road excavation on 2nd Street west of Olive Street in Stage 3.
  • Began Stage 3 light pole base construction.
  • Took overhead power lines offline and prepared to remove the utility poles and lines. Once all lines are cleared, the poles will be taken down.

Upcoming work

  • Continue Stage 3 light pole and banner pole base work.
  • Continue road excavation on 2nd Street west of Olive Street.
  • Install drain tile, irrigation and electrical conduits on 2nd Street west of Olive Street in Stage 3.
  • Begin storm sewer installation in the alley between Olive Street and Elm Street.
  • Remove overhead power poles.
    • Affected properties will be notified with specifics.
    • During the workday, best efforts will be made to accommodate regular access as much as possible.

August 1, 2025

Completed work

  • Continued Stage 3 utility work (water main, sanitary sewer and storm sewer installation) on Olive Street.
  • Continued Stage 2 restoration work.
  • Continued preparation work for burying overhead utilities on Olive Street with placement of the transformer and removal of overhead utilities.

Upcoming work

  • Continue Stage 3 utility work (sanitary sewer and water main) on 2nd Street between Olive Street and Elm Street.
    • During utility connection work, water shutoffs may be needed to connect properties to the existing water system. Affected properties will be notified prior to shutoffs.
  • Continue preparation work for burying overhead utilities on Olive Street with placement of the transformer and removal of overhead utilities.
    • Affected properties will be notified with specifics.
    • During the workday, best efforts will be made to accommodate regular access as much as possible.

July 25, 2025

Completed work

  • Continued Stage 3 utility work on 2nd Street west of Olive Street.
  • Continued Stage 1 and 2 restoration work.
  • CenterPoint completed relocating gas main in the alley between Olive Street and Elm Street.
  • Continued preparation work for burying overhead utilities on Olive Street with placement of the transformer and removal of overhead utilities.

Upcoming work

  • Continue Stage 3 utility work on Olive Street and 2nd Street.
    • During utility connection work, water shutoffs may be needed to connect properties to the existing water system. Affected properties will be notified prior to shutoffs.

PROJECT EMAIL/TEXT UPDATES

Sign me up!

CONTACT

JON HAUKAAS, DIRECTOR OF PUBLIC SERVICES

City of Waconia

jhaukaas@waconia.org

952-442-4265

 

COLTON LEE, PROJECT MANAGER

Bolton & Menk, Inc.

colton.lee@bolton-menk.com

612-346-6059

 

JAKE SAULSBURY, P.E., CITY ENGINEER

Bolton & Menk, Inc.

jake.saulsbury@bolton-menk.com

612-756-4319