City of Waconia Downtown Reconstruction Project
Top
 

Project Updates

Project Updates – June 5, 2026

This week in Stage 1, crews continued water and sanitary sewer installation work. Sidewalk removals, light and banner pole bases installations and watermain connections on Elm Street were completed.

Next week, crews plan to continue installing light and banner pole bases. Work is also planned for storm sewer installations, street excavation and irrigation system installations.

Please contact our on-site project representative, Dalmas Omwoyo at 651-728-0312, with any questions, property specific needs or accommodations.

Map of construction stages, click to view larger image
Map of construction stages

May 29, 2026

This week crews continued sanitary sewer and water service work in Stage 1, and is expected to finish next week. As a reminder, water shutoffs may be necessary during this work. Properties will be notified in advance of any impacts. During the workday, crews will do their best to accommodate regular access.

Next week, crews plan to work on storm sewer, sidewalk removals and light and banner pole base installation in Stage 1. Access to front doors will be limited during this work. Areas will be restored with temporary walking mats when complete. During the workday, crews will do their best to accommodate regular access.

May 27, 2026

On Thursday, May 28 and Friday, May 29, crews will complete concrete maintenance work in the 2023 construction area (two blocks of Main Street and one block of Olive Street).

During this time, some parking stalls and sidewalk segments will be temporarily blocked. Pedestrians will be directed to alternate routes.

Once the work is completed, sidewalks and parking stalls will be restored to their original condition. However, any newly placed concrete will be marked off and remain closed for approximately 7 days to allow the concrete to harden.

The time and day of concrete work is subject to change due to weather or contractor scheduling changes. Properties will receive further notice if such changes occur. We apologize for any inconvenience this may cause and appreciate your patience and understanding!

Click image to view larger version.

May 22, 2026

This week crews finished installing the sewer and water mains on Stage 1. Late this week crews began installing sewer and water services on Stage 1. This work began on First Street at Olive Street and will continue to the east for all of next week.

Reminder: Water shutoffs may be necessary during this work. Properties will be notified in advance of any impacts. During the workday, crews will do their best to accommodate regular access.

May 15, 2026

Stage 1 watermain work continued and is almost complete up to Pine Street. Watermain testing will occur in the coming days with water service work beginning late next week or the week of May 26.

Water shutoffs may be necessary during this work. Properties will be notified in advance of any impacts. During the workday, crews will do their best to accommodate regular access.

May 7, 2026

This week, crews completed roadway removals in the Stage 1 area and started sanitary sewer work between Olive Street and Pine Street. Over the coming week, crews will begin watermain installation in the Stage 1 area.

Xcel Energy was also on site this week to remove and relocate poles on 1st Street and 2nd Street that conflict with future construction activities.

During utility connection work, water may need to be turned off to some properties to connect it to the existing water system. The affected properties will be notified prior to these occurrences. During the workday, crews will work to accommodate regular access as much as possible.

PROJECT EMAIL/TEXT UPDATES

Sign me up!

CONTACT

JON HAUKAAS, DIRECTOR OF PUBLIC SERVICES

City of Waconia

[email protected]

952-442-4265

 

COLTON LEE, PROJECT MANAGER

Bolton & Menk, Inc.

[email protected]

612-346-6059

 

JAKE SAULSBURY, P.E., CITY ENGINEER

Bolton & Menk, Inc.

[email protected]

612-756-4319