190th Street Trail

Project Summary:

The City of Jordan is undertaking a construction project to construct a new 8’ wide bituminous (asphalt/blacktop) trail along 190th Street from CR9 to Beaumont Avenue this summer. Completion of this trail connection is a long-desired goal of the community as it will more directly and safely connect pedestrians and bicyclists with County Road 9 and the rest of the community. Funding for the project is largely from external contributions, including a grant received from the Shakopee Mdewakanton Sioux Community (SMSC) and funding from developers who have built along 190th Street in years past.

The project includes private utility relocation, minor storm sewer and drainage improvements, site grading, addition of curb and gutter to portions of 190th Street, street patching, trail paving, ADA Improvements, and turf restoration.


Project Documents:

Project Location Map 

Project Newsletter 1 


Project Status, Schedule, Updates:

Favorable bids for the work were received on May 7, 2020 and the project was awarded to S.M. Hentges & Sons, Inc. from Jordan, Minnesota on June 1, 2020.

S.M. Hentges & Sons, Inc. is currently scheduled to begin work the week of June 13th.  Most work is expected to be completed by late August. Some miscellaneous cleanup and items may span into the early fall.

The approximate project schedule provided to the City is below. Please note that this schedule is weather dependent, and the contractor’s schedule may change. Additional notifications will be made to adjacent residents with any significant changes to the contractor’s provided schedule.

Early July: Private Utility Relocation

Mid-July: Trail Construction Begins

Late July: Grading of trail, storm sewer and related drainage work, trail gravel base construction

August: Concrete Curb and Gutter along existing turn lane portions of 190th trail, street patching, and trail paving

Late August / September: Turf restoration and site cleanup


Project Contacts:

Luke Wheeler, of Bolton & Menk, will be primary contact representing the City and its residents and business owners.  If you have any questions regarding the project you may contact him at (612) 597-9105 or Luke.Wheeler@bolton-menk.com.

Mike Waltman, of Bolton & Menk is the Jordan City Engineer and Project Manager.  He can be reached at (952) 890-0509 or mikewa@bolton-menk.com


FAQ’S

Q: How long will this project take?

A: Construction is expected to begin in Mid-July with a bulk of the work completed by late August or Early September. Some remaining clean up work may stretch into the fall. A more detailed schedule can be seen above under the “Project Status, Schedule, Updates” section of this website. Please note that the contractor’s schedule may change. The project team will do their best to keep residents informed with the most up to date schedule.

 Q: What work will be done?

A: The project includes private utility relocation, minor storm sewer and drainage improvements, site grading, addition of curb and gutter to portions of 190th Street, street patching, trail paving, ADA Improvements, and turf restoration.

 Q: When will the contractor be working?

A: City working hours are 7 AM to 7 PM M-F and 8 AM to 6 PM on Saturday as necessary

 Q: Is there someone I can talk to about the construction?

A: Luke Wheeler, of Bolton & Menk, will be primary contact representing the City and its residents and business owners.  If you have any questions regarding the project you may contact him at (612) 597-9105 or Luke.Wheeler@bolton-menk.com.

 Mike Waltman, of Bolton & Menk is the Jordan City Engineer and Project Manager.  He can be reached at (952) 890-0509 or mikewa@bolton-menk.com