2026 Infrastructure Improvements
Construction Update
June 19, 2026
Construction on the City of Jordan’s 2026 Infrastructure Improvements project began this week and the contractor is making great progress, despite some wet weather! Please see below for a summary of the work completed this week, what to expect next week, and some general information to be aware of.
Week of June 15
- Removal of curb and gutter and pedestrian ramps have been completed on Ervin Industrial Dr, Enterprise Dr, Corporate Dr, 185th St, the eastern half of Timberline Neighborhood, and the Bridle Creek/Arborview Neighborhood.
- All curb and gutter has been replaced on Ervin Industrial Dr, Enterprise Dr, Corporate Dr, and 185th St.
- Removals of curb and gutter and pedestrian ramps have been marked (pink paint) in Sawmill Woods. The contractor began saw cutting on Friday in preparation of removals.
Week of June 22
- The concrete crew will continue to install concrete curb and gutter and pedestrian ramps on Ervin Industrial Ave, the eastern half of Timberline, and then Bridle Creek/Arborview.
- Once concrete curb and gutter installation is complete, crews will install a bituminous (asphalt) patch in front of newly poured curb and gutter. This work will be completed on Ervin Industrial Dr, Enterprise Dr, Corporate Dr, 185th St, and tentatively the eastern half of Timberline.
- Removals of curb and gutter and pedestrian ramps are planned to start mid-week in the Sawmill Woods area. Crews are anticipating installing portions of Sawmill Woods curb and gutter at the end of the week, into the following week.
General Notes
- No parking is allowed near these removal/new concrete sections during construction. Please move all vehicles away from marked/newly constructed areas by 7 a.m. each day.
- New concrete curbs, gutters, and pedestrian ramps cannot be driven or parked on for 7 days. This gives the concrete time to cure and harden.
- If sections of concrete curb and gutter at your driveway have been replaced, you may be required to park on the street while the concrete cures.
- Please refrain from walking, riding bikes, etc. on new concrete for 24 hours after it has been poured.
- If you happen to step in the fresh concrete, please contact the project team immediately, repairs can sometimes be made depending on the stage of the curing process.
- If your irrigation system has been impacted, please contact Dylan Anderson (651-416-6176). Feel free to text Dylan with a photo(s) and the address of the impacted irrigation. We will be documenting damages and coordinating with property owners to have the irrigation repaired, once construction in the area is almost complete.
Sign Up for Project Updates
Background
The City of Jordan is planning to make improvements to various streets and alleys during the summer of 2026 (see map above). The project design will be completed throughout the fall of 2025 and winter of 2026. The project is planned to go out for bid in the spring of 2026 and construction is expected to begin sometime after June 1st, 2026 and be completed by the fall of 2026. The project scope generally includes:
Alleys
- Grading/drainage improvements
- The addition of storm sewers in areas where surface drainage cannot be achieved
- Concrete paving of the alley
Street Resurfacing
- Resurfacing of street pavement (method as noted in the map above)
- Spot removal and replacement of deficient curb and gutter segments
- Replacement of concrete pedestrian ramps for compliance with the Americans with Disabilities Act (ADA)
Documents
- Project Newsletter (Start of Construction) – 6/4/26
- Council Meeting Content: 3A, 9A, 9B – Assessment Hearing, Adopting Assessments, Awarding Construction Contract – 5/26/26
- Pre-Recorded Public Information Presentation for 5/19/26 Public Info Meeting
- May 19th, 2026 Public Information Meeting invite
- Council Meeting Content: 13D – Present Bids, Order Final Assessment Roll, Order Assessment Hearing – 4/27/26
- Council Meeting Content: 3A – Public Improvement Hearing and 9A – Order Final Plans – 01/26/2026
- Public Information Meeting Invite – 01/21/2026
- Public Information Meeting Comment Card – 01/21/2026
- Pre-Recorded Public Information Presentation – 01/21/2026
- Council Meeting Content: 8A – Receive Feasibility Study and Order Public Improvement Hearing – 01/12/2026
- Feasibility Report
- Overall Project Area map
- Project Sub-Areas Maps
- Council Meeting Content: Authorization of Feasibility Study for 2026 Infrastructure Improvements – 10/13/2025
- Project Initiation Letter to Residents
- Preliminary Resident Questionnaire (Print Version)
- Preliminary Resident Questionnaire (Digital Version)
Schedule
- Fall 2025: Preliminary Data Collection
- November 2025 – January 2026: Preliminary Engineering
- January 2026: Public Open House #1
- January – April 2026: Final Design
- April 2026: Bidding
- May 2026: Public Open House #2
- Summer 2026: Construction
Contacts
Luke Wheeler
City Engineer
Bolton & Menk
(612) 597-9105
[email protected]